WESDOME ANNOUNCES DRILL RESULTS FROM KIENA COMPLEX AND UPDATES RAMP DEVELOPMENT PROGRESS
WESDOME ANNOUNCES DRILL RESULTS FROM KIENA COMPLEX
AND UPDATES RAMP DEVELOPMENT PROGRESS

Toronto, Ontario – June 21, 2017 – Wesdome Gold Mines Ltd. (TSX: WDO) (“Wesdome” or the “Company”) is pleased to provide an update on underground drilling activities and upcoming exploration ramp development at its 100% owned Kiena Mine Complex, in Val d'Or, Quebec.

On May 3, 2017, Wesdome announced plans to drive an exploration ramp to provide enhanced drill coverage of the Kiena Deep discovery, which remains open at depth and along strike. The ramp is scheduled to commence in August and take 9 – 10 months to complete (see Figures 1, 2 and 3). The company has received bids from six qualified contractors with the aim to award the ramp development work by July 1st. As it currently stands, the Kiena Deep target cannot be traced further efficiently from existing workings. The Company expects to have initial new drill stations available to restart Kiena Deep drilling as early as September – October, 2017, concurrent with ramp development activities.

The present drill program encompasses 2 drills tracing auxiliary targets, which are close to existing workings, open at depth, and demonstrate near-term development potential (see Figures 4, 5 and 6).

Mr. Duncan Middlemiss, President and CEO, commented “The two drills currently underground at Kiena will focus on drilling other prospective targets including the VC and S50 Zones, which are located close to existing infrastructure. The current pause on the Kiena Deep exploration gives the Company ample opportunity to further delineate existing resources which could potentially aid in a recommencement of production in the short to mid-term. Kiena has a strong resource base from which to work, with measured and indicated resources of 2.5M tonnes @ 5.59 g/t Au for 449,300 ounces contained and inferred resources of 1.6M tonnes @ 7.97 g/t Au for 400,400 ounces contained. It is a large property with three former producing mines and eight shafts located within. We believe the Kiena Deep Zone may be the anchor which establishes future production and allows for a thorough examination of this high potential property.”

RECENT KIENA DEEP DRILLING RESULTS (Table 1)

Recently received results support a north extension of the Kiena Deep A Zone proximal to the basalt-komatiite contact (Figures 1 and 3). Highlights include:

Kiena Deep – Open to North (Figure 1)

  • 12.81 g/t uncut over 8.8 m core length (8.38 g/t cut) in hole 6166
  • 5.19 g/t uncut over 14.3 m core length (5.19 g/t cut) in hole 6179, Including 11.38 g/t over 5.2 m uncut (11.38 g/t cut)

Assays are cut to an arbitrary 34.28 g/t and true widths are currently undetermined

AUXILIARY TARGETS

The Company is currently drilling the VC Zone at depth and the S50 Zone where it is immediately accessible from the 960 m level and the 980 m level. At shallower depths there is identified potential for the S50 southeast lens and the South Zone, which remain open below 330 m level.

1) VC Zone – 670 m to 1100 m levels (Figure 4)

This zone remains open at depth. Previous results include the following highlights (see press release dated June 13, 2012):

  • 5.41 g/t uncut over 10.6 m true width (5.41 g/t cut) in hole U4539
  • 7.18 g/t uncut over 10.3 m true width (7.13 g/t cut) in hole U5813

Partial assay results have been received from our first hole drilled in 2017.

  • 8.23 g/t over 5.3 m uncut (8.23 g/t cut) in hole 6192

2) S50 Zone – immediately accessible target 960 m – 1100 m level (Figure 6)

Preliminary results include:

  • 5.00 g/t over 11.7 m uncut (5.00 g/t cut) in hole 6145A
  • 3.89 g/t over 8.0 m uncut (3.89 g/t cut) in hole 6147
  • 4.12 g/t over 14.8 m uncut (3.50 g/t cut) in hole 6165
  • 5.92 g/t over 7.0 m uncut (5.92 g/t cut) in hole 6168
  • 10.34 g/t over 9.2 m uncut (8.13 g/t cut) in hole 6188

3) S50 Southeast Lens – open below 330 m level (Figure 5)

Highlights include:

  • 6.80 g/t uncut over 18.5 m core length (6.80 g/t cut) in hole U4115
  • 4.91 g/t uncut over 16.6 m core length (4.91 g/t cut) in hole U4117

4) South Zone – open below 330 m level (Figure 5)

Previous limited drilling returned the following highlights (press-release dated January 2, 2013)

  • 21.07 g/t uncut over 7.5 m core length (8.60 g/t cut) in hole U5454
  • 10.59 g/t uncut over 5.1 m core length (8.86 g/t cut) in hole U5445
  • 11.40 g/t uncut over 3.5 m core length (11.40 g/t cut) in hole U5411
THE KIENA COMPLEX
The Kiena Mine Complex is a fully permitted, integrated mining and milling infrastructure which
includes a 930 metre production shaft and 2,000 tonne per day capacity mill. From 1981 to 2013 the
mine produced 1.75 million ounces of gold from 12.5 million tonnes at a grade of 4.5 g/t. The bulk
of this production came from the S-50 Zone between depths of 100 and 1,000 metres. In 2013,
operations were suspended due to a combination of declining gold prices and lack of developed
reserves. The infrastructure has been well preserved on care and maintenance status.
TECHNICAL DISCLOSURE
The technical and scientific disclosure in this press release has been prepared and approved by Marc
Ducharme, P. Geo.(OGQ #597), Chief Exploration Geologist of Wesdome and "Qualified Person"
as defined by National Instrument 43-101 disclosure standards. Analytical work was performed by
Techni-Lab (ActLabs) of Ste-Germaine-Boulé (Quebec), a certified commercial laboratory (SCC
Accredited Lab #707). Sample preparation was done at Techni-Lab (ActLabs) in Val d'Or (Quebec)
and assaying was done by fire assay methods at Techni-Lab (ActLabs) laboratory in Ste-Germaine-
Boulé (Quebec). In addition to laboratory internal duplicates, standards and blanks, the geology
department inserts blind duplicates, standards and blanks into the sample stream at a frequency of
one in twenty to monitor quality control.
Resources Reference: 43-101 Technical Report, December 16, 2015 available at www.sedar.com

ABOUT WESDOME

Wesdome Gold Mines is in its 31st year of continuous gold mining operations in Canada. The Company is 100% Canadian focused with a pipeline of projects in various stages of development. The Eagle River Complex near Wawa, Ontario is currently producing gold from two mines, the Eagle River Underground Mine and the Mishi Open pit, from a central mill. Wesdome is actively exploring its brownfields asset, the Kiena Complex in Val d’Or, Quebec. The Kiena Complex is a fully permitted former mine with a 930 metre shaft and 2,000 tonne per day mill. The Company has further upside at its Moss Lake gold deposit, located 100 kilometres west of Thunder Bay, Ontario, which is being explored and evaluated to be developed in the appropriate gold price environment. The Company has approximately 133 million shares issued and outstanding and trades on the Toronto Stock Exchange under the symbol “WDO.”

For further information, please contact:

Duncan Middlemiss or Lindsay Carpenter Dunlop President and CEO VP Investor Relations 416-360-3743 ext. 29 416-360-3743 ext. 25 [email protected] [email protected]

8 King St. East, Suite 811 Toronto, ON, M5C 1B5 Toll Free: 1-866-4-WDO-TSX Phone: 416-360-3743, Fax: 416-360-7620 Website: www.wesdome.com

This news release contains “forward-looking information” which may include, but is not limited to, statements with respect to the future financial or operating performance of the Company and its projects. Often, but not always, forward-looking statements can be identified by the use of words such as “plans”, “expects”, “is expected”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or variations (including negative variations) of such words and phrases, or state that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward- looking statements involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by the forward-looking statements. Forward- looking statements contained herein are made as of the date of this press release and the Company disclaims any obligation to update any forward-looking statements, whether as a result of new information, future events or results or otherwise. There can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. The Company undertakes no obligation to update forward-looking statements if circumstances, management’s estimates or opinions should change, except as required by securities legislation. Accordingly, the reader is cautioned not to place undue reliance on forward-looking statements.

Table 1: Kiena Drilling Results

Core length Hole No. From (m) To (m) (m) Grade* Assay Cut Target (g/t Au) (g/t Au)
61400.826.025.32.892.89S-50
Including21.023.02.012.1612.16S-50
614040.045.05.01.701.70S-50
614053.062.09.02.372.37S-50
614064.590.025.51.111.11S-50
6140100.5116.816.31.021.02Kiena Deep Sector
6140122.5123.51.02.022.02Kiena Deep Sector
6140192.5196.13.63.253.25Kiena Deep Sector
6140348.7350.21.52.722.72Kiena Deep Sector
6140395.5403.07.51.881.88Kiena Deep Sector
6140420.0426.56.52.732.73Kiena Deep Sector
6140442.0445.03.03.203.20Kiena Deep Sector
6140452.5459.06.51.731.73Kiena Deep Sector
6140472.0480.08.01.991.99Kiena Deep Sector
6140615.0619.04.02.662.66Kiena Deep Sector
6140644.0646.02.05.685.68Kiena Deep Sector
6140683.0685.02.02.242.24Kiena Deep Sector
6140712.5715.42.92.562.56Kiena Deep Sector
6140729.0733.04.01.541.54Kiena Deep Sector
6140739.0745.26.21.611.61Kiena Deep Sector
6141523.5528.95.42.032.03Kiena Deep Sector
6142550.5552.01.51.501.50Kiena Deep Sector
6142564.0574.910.90.310.31Kiena Deep Sector
6142661.5662.81.31.621.62Kiena Deep Sector
614367.570.02.51.181.18Kiena Deep Sector
614379.081.02.02.522.52Kiena Deep Sector
614387.589.01.54.064.06Kiena Deep Sector
6143295.5297.01.51.261.26Kiena Deep Sector
6143329.0330.01.04.724.72Kiena Deep Sector
6143388.0388.90.93.403.40Kiena Deep Sector
6143423.0424.51.51.091.09Kiena Deep Sector
6143456.8460.84.02.902.90Kiena Deep Sector
6143456.8474.818.00.930.93Kiena Deep Sector
6143524.0525.01.012.2712.27Kiena Deep Sector
6143562.5564.01.50.990.99Kiena Deep Sector
6143588.0591.03.01.331.33Kiena Deep Sector
6144354.2355.51.35.695.69Kiena Deep Sector
6144372.0373.51.54.974.97Kiena Deep Sector
6144385.5387.01.51.761.76Kiena Deep Sector
61450.020.420.42.052.05S-50
6145A1.049.548.52.482.48S-50
Including1.012.711.75.005.00S-50
6145A60.073.913.91.651.65Kiena Deep Sector
6145A88.590.52.01.061.06Kiena Deep Sector
6145A354.0370.016.00.800.80Kiena Deep Sector
6145A419.6421.51.91.231.23Kiena Deep Sector
6146279.6280.50.91.091.09Kiena Deep Sector
6146394.5396.01.51.531.53Kiena Deep Sector
61470.024.024.02.612.61S-50
61477.015.08.03.893.89S-50
614728.530.01.52.252.25S-50
614736.037.51.51.251.25S-50
614763.067.54.51.551.55S-50
6147113.5115.01.52.862.86Kiena Deep Sector
6147161.5167.56.01.061.06Kiena Deep Sector
6147221.5222.51.01.071.07Kiena Deep Sector
6147266.5268.52.02.642.64Kiena Deep Sector
6147354.0361.07.01.061.06Kiena Deep Sector
6147365.5367.01.51.071.07Kiena Deep Sector
6147439.4447.07.61.001.00Kiena Deep Sector
6147466.0471.05.00.970.97Kiena Deep Sector
6147526.0527.01.03.263.26Kiena Deep Sector
6148399.7401.01.31.231.23Kiena Deep Sector
6149167.0177.010.00.610.61Kiena Deep Sector
6149195.0204.09.00.910.91Kiena Deep Sector
6149399.0403.04.00.430.43Kiena Deep Sector
615058.560.01.51.951.95Kiena Deep Sector
6151148.5150.01.51.181.18Kiena Deep Sector
6151157.5159.01.51.451.45Kiena Deep Sector
6151403.8405.01.22.832.83Kiena Deep Sector
6152183.2185.92.72.782.78Kiena Deep Sector
6152222.0225.03.00.500.50Kiena Deep Sector
6152240.0243.03.01.821.82Kiena Deep Sector
6153289.5291.01.51.321.32Kiena Deep Sector
6153316.5318.01.51.791.79Kiena Deep Sector
6153364.5365.91.45.205.20Kiena Deep Sector
6154110.8112.31.53.313.31Kiena Deep Sector
6154415.9416.91.01.921.92Kiena Deep Sector
6154423.9425.11.22.542.54Kiena Deep Sector
615574.579.04.51.501.50Kiena Deep Sector
6155219.0225.06.00.830.83Kiena Deep Sector
Including223.5225.01.52.102.10Kiena Deep Sector
6155489.0492.03.01.501.50Kiena Deep Sector
615651.057.06.01.801.80Kiena Deep Sector
6156157.5159.01.55.735.73Kiena Deep Sector
6156313.5315.01.56.406.40Kiena Deep Sector
6156431.5432.51.01.151.15Kiena Deep Sector
6157A40.546.56.00.880.88Kiena Deep Sector
6157A75.576.00.51.671.67Kiena Deep Sector
6157A88.590.01.51.611.61Kiena Deep Sector
6157A138.0139.81.84.984.98Kiena Deep Sector
6157A283.5285.52.01.051.05Kiena Deep Sector
6157A340.9342.01.11.771.77Kiena Deep Sector
6157A387.5388.00.52.382.38Kiena Deep Sector
6157A492.0494.02.01.631.63Kiena Deep Sector
6157A504.1508.03.91.801.80Kiena Deep Sector
615875.076.51.51.361.36Kiena Deep Sector
6158234.7236.01.35.195.19Kiena Deep Sector
6158376.5377.71.229.6029.60Kiena Deep Sector
6158407.0415.08.01.711.71Kiena Deep Sector
6158594.0595.01.08.268.26Kiena Deep Sector
6158637.5639.01.52.252.25Kiena Deep Sector
6158678.0679.51.51.361.36Kiena Deep Sector
615963.069.06.02.042.04Kiena Deep Sector
6159403.5405.01.52.082.08Kiena Deep Sector
6159423.0427.04.01.541.54Kiena Deep Sector
6159432.0439.07.00.840.84Kiena Deep Sector
6160351.0352.51.50.220.22Kiena Deep Sector
61610.09.09.02.282.28S-50
616114.021.07.01.621.62S-50
616127.029.52.51.821.82S-50
616151.554.53.01.701.70Kiena Deep Sector
616160.763.83.11.821.82Kiena Deep Sector
6161A1.032.031.02.192.19S-50
Including22.030.58.54.124.12S-50
6161A34.536.52.017.5317.53S-50
6161A38.540.52.01.311.31S-50
6161A50.551.61.11.831.83S-50
6161A171.5173.01.518.2218.22Kiena Deep Sector
6162369.0372.03.00.460.46Kiena Deep Sector
6162720.5723.53.00.580.58Kiena Deep Sector
6162735.5738.53.03.743.74Kiena Deep Sector
6162743.0744.51.50.550.55Kiena Deep Sector
6164151.8153.31.52.312.31Kiena Deep Sector
6164308.5310.92.44.914.91Kiena Deep Sector
6164344.9347.12.26.006.00Kiena Deep Sector
6164369.0370.01.01.131.13Kiena Deep Sector
61650.014.814.84.123.50S-50
Including0.02.02.022.7618.19S-50
616666.472.66.23.663.66Kiena Deep Sector
6166135.5144.18.60.260.26Kiena Deep Sector
6166486.0487.01.042.7734.28Kiena Deep Sector
6166499.0509.910.91.681.68Kiena Deep Sector
Including499.0500.11.13.033.03Kiena Deep Sector
6166504.1505.11.05.925.92Kiena Deep Sector
6166509.0509.90.97.097.09Kiena Deep Sector
6166519.2528.08.812.818.38Kiena Deep Sector
6166543.6547.03.412.688.72Kiena Deep Sector
6167301.4301.90.51.831.83Kiena Deep Sector
61681.019.018.03.063.06S-50
Including1.08.07.05.925.92S-50
616830.036.06.01.951.95S-50
616842.544.01.52.942.94S-50
616865.567.01.53.583.58S-50
6168245.0246.51.51.031.03Kiena Deep Sector
616962.865.12.31.541.54Kiena Deep Sector
6169157.8159.31.50.490.49Kiena Deep Sector
6169462.5465.53.01.211.21Kiena Deep Sector
6169626.3635.08.72.612.61Kiena Deep Sector
Including626.3628.52.28.888.88Kiena Deep Sector
6169785.1786.61.56.246.24Kiena Deep Sector
6169789.6791.11.53.393.39Kiena Deep Sector
6169976.5978.01.52.702.70Kiena Deep Sector
61691003.01003.80.81.081.08Kiena Deep Sector
6171308.8314.05.23.853.85Kiena Deep Sector
6171324.7325.71.07.917.91Kiena Deep Sector
6171458.0463.05.00.320.32Kiena Deep Sector
6171489.9490.60.74.484.48Kiena Deep Sector
6172321.5322.51.04.944.94Kiena Deep Sector
6173A69.077.58.56.016.01Kiena Deep Sector
6173A328.0329.01.05.965.96Kiena Deep Sector
6173A421.5432.010.51.891.89Kiena Deep Sector
6173A453.9456.82.90.310.31Kiena Deep Sector
6174413.5414.51.02.482.48Kiena Deep Sector
6174455.9466.710.82.642.64Kiena Deep Sector
Including455.9460.54.64.894.89Kiena Deep Sector
6174474.9478.23.30.730.73Kiena Deep Sector
6174484.2486.52.32.892.89Kiena Deep Sector
6174504.8507.93.12.022.02Kiena Deep Sector
6174516.5523.26.70.830.83Kiena Deep Sector
Including516.5517.81.32.532.53Kiena Deep Sector
6174530.0540.210.21.211.21Kiena Deep Sector
6176A257.1258.61.51.091.09Kiena Deep Sector
6176A267.3268.81.51.171.17Kiena Deep Sector
6176A295.2296.51.32.282.28Kiena Deep Sector
6177329.0330.51.51.661.66Kiena Deep Sector
6177346.0349.03.04.974.97Kiena Deep Sector
6177346.1347.00.915.8215.82Kiena Deep Sector
6177414.5419.04.51.431.43Kiena Deep Sector
6177470.0471.01.01.011.01Kiena Deep Sector
6177493.6514.020.41.641.64Kiena Deep Sector
6177523.2524.71.55.325.32Kiena Deep Sector
6178343.4344.41.01.761.76Kiena Deep Sector
6178391.2391.70.58.348.34Kiena Deep Sector
6178408.0409.91.946.1825.57Kiena Deep Sector
6178444.0454.510.52.802.80Kiena Deep Sector
6178472.5474.01.51.581.58Kiena Deep Sector
6178477.0480.03.04.464.46Kiena Deep Sector
6178489.0501.012.01.511.51Kiena Deep Sector
6178519.4522.53.13.343.34Kiena Deep Sector
6178542.9544.11.21.971.97Kiena Deep Sector
6178552.1558.36.21.381.38Kiena Deep Sector
6178572.4575.22.81.251.25Kiena Deep Sector
6178600.5601.40.91.241.24Kiena Deep Sector
6179124.5126.01.51.571.57Kiena Deep Sector
6179395.5397.01.51.861.86Kiena Deep Sector
6179419.6420.61.015.7215.72Kiena Deep Sector
6179427.0428.01.03.793.79Kiena Deep Sector
6179432.0433.01.07.117.11Kiena Deep Sector
6179488.1489.51.41.411.41Kiena Deep Sector
6179524.7539.014.35.195.19Kiena Deep Sector
Including524.7529.95.211.3811.38Kiena Deep Sector
6179546.0547.01.05.335.33Kiena Deep Sector
618061.563.01.52.512.51Kiena Deep Sector
6180411.0412.51.51.471.47Kiena Deep Sector
6180424.8426.01.21.211.21Kiena Deep Sector
6180447.0448.51.52.792.79Kiena Deep Sector

6180 504.6 506.1 1.5 2.91 2.91 Kiena Deep Sector

6180536.0540.54.512.698.19Kiena Deep Sector
6183127.5129.01.53.433.43Kiena Deep Sector
6183127.5129.01.53.433.43Kiena Deep Sector
6183318.0320.42.41.391.39Kiena Deep Sector
6184497.4501.54.14.544.54Kiena Deep Sector
6186432.4433.41.072.4534.28Kiena Deep Sector
61883.012.29.210.348.13S-50
Including3.08.45.416.9113.14S-50
61894.04.80.82.302.30S-50
61895.711.05.32.972.97S-50
619224.028.64.62.282.28VC Zone †
619232.537.85.38.238.23VC Zone †
  • Assay intervals include values cut to an arbitrary, historic 1 oz / ton or 34.28 g/t Au

† Partial assay results