Friday, October 16, 2026
MiningNewsTerminal
Friday, October 16, 2026 Admin

TK.V ·

Tinka Reports Updated PEA and Mineral Resource Estimate for the Ayawilca Polymetallic Zinc‐tin‐silver Deposit

Resource Estimates Technical Reports (NI 43-101) Economic Studies

T: 604.685.9316    [email protected]

NEWS RELEASE  TSXV & BVL: TK   OTCQB: TKRFF

February 28, 2024

TINKA REPORTS UPDATED PEA AND MINERAL RESOURCE ESTIMATE FOR THE AYAWILCA POLYMETALLIC  ZINC‐TIN‐SILVER DEPOSIT  

Vancouver,  Canada – Tinka Resources  Limited (“Tinka” or the “Company”) (TSXV & BVL: TK) (OTCQB: TKRFF) is pleased to announce the results from an updated Preliminary Economic Assessment (“PEA”) on the Company’s 100%‐ owned polymetallic Ayawilca project (“Ayawilca” or the “Project”) in central Peru. The updated PEA shows Ayawilca

e an excellent base metals project with significant enhancements from the previous PEA study.The Project now
ures a smaller, more efficient zinc‐silver‐lead plant, introduces a separate tin plant for additional revenue an
modity diversification and highlights the development path forward for Ayawilca to become a producing mine.

PEA Highlights: 

  • Robust economics: After‐tax Net Present Value (“NPV”) at 8% discount of US$434 million (pre‐tax NPV8% of US$732 million) and after‐tax Internal Rate of Return (“IRR”) of 25.9% (pre‐tax IRR of 34.8%).
  • Payback period after‐tax of 2.9 years (pre‐tax of 2.4 years).
  • Initial Capital Expenditure (“Capex”) of US$382 million.
  • Long 21‐year life of mine (“LOM”) for a 2.0 million tonnes per annum (Mtpa) zinc‐silver‐lead operation with 15‐years of tin production at 0.3 Mtpa.
  • Average C1 cash cost of US$0.55/pound zinc and all in sustaining cost (“AISC”) of US$0.68/ pound zinc.
  • Average annual metal production (in concentrate) of 200 million pounds of zinc (90,000 tonnes Zn), 3.26 million pounds of tin (1,500 tonnes Sn), 560,000 ounces of silver and 5.7 million pounds of lead (2,590 tonnes Pb).
  • Zinc Zone Indicated Mineral Resource tonnage increased 49% from the previous Mineral Resource estimate.
  • Tin Zone Indicated Mineral Resource declared for the first time.
  • Excellent location in a world‐class mining jurisdiction, close to a zinc smelter and port.
  • Compact mine footprint and planned use of filtered tailings technology provides the lowest risk and most water‐efficient solution for tailings storage while 40% of tailings to be stored underground as backfill.

Dr. Graham Carman, Tinka’s President and CEO, stated:

“We are very pleased to release the results of the updated 2024 PEA for the Ayawilca project.  We believe the results of  the PEA show Ayawilca to be an outstanding polymetallic project with several improvements from the previous study. 

le zinc continues to be the primary revenue source, Ayawilca's polymetallic nature includes important contribution
tin and silver providing valuable commodity diversification.The updated PEA is marked by the incorporation of
ller, more efficient, zinc‐silver‐lead plant and a separate tin plant and a more compact mine footprint. Despite a
ease in the initial capex, due to efficiencies in the mine design there was no significant impact on valuation. Th
ng financial metrics include an after‐tax NPV8% of US$434 million, an after‐tax IRR of 25.9%, and a post‐tax paybac
od of only 2.9 years which highlight the potential for Ayawilca to become a producing mine.”

“A revised Mineral Resource estimation has significantly improved the level of confidence in the resource as a result of  an additional 11,000 metres of drilling completed in 2023. The Zinc Zone Indicated Mineral Resource tonnage has  increased 49% over the previous estimate while zinc content has increased by 22% and silver content by 45%.  The Tin  Inferred Mineral Resource has increased in tonnage and metal content by 51% and 13%, respectively, while a Tin  Indicated Mineral Resource is declared for the first time. The Company has chosen to adopt the highest standard for  reporting underground mine resources to satisfy the “Reasonable Prospects for Eventual Economic Extraction (RPEEE)”  as required by CIM (2014) in the demonstration of spatial continuity of mineralization within potentially mineable  shapes (i.e., stopes). With the market increasingly moving towards RPEEE resource reporting for underground deposits,  we are adopting this method of resource reporting for the first time.” 

“The use of filtered tailings is the lowest risk and most water‐efficient solution for tailings storage at surface, and  highlights our commitment to minimize environmental risks.  The storage of a substantial quantity of tailings as backfill  underground also reduces surface tailings storage, again helping to minimize the environmental impact.”  

”There remains significant exploration potential for further discoveries at Ayawilca, and several of the resource bodies  remain open at depth, with a potential feeder system remaining largely untested by drilling particularly at the Tin Zone.” 

The  results  of  the  PEA  update  will  be  disclosed  in  an  independent  technical  report  in  accordance  with  National Instrument 43‐101 Standards of Disclosure for Mineral Projects (“NI 43‐101”) and prepared by independent consulting firm SRK Consulting (UK) (“SRK”) with specific subject matter expertise including Transmin Metallurgical consultants (“Transmin”), Envis Peru S.A.C. (“Envis”) tailings consultants and MineFill Services (“MineFill”) backfill consultants.  SLR Consulting (Canada) Ltd (“SLR”) has prepared the updated Mineral Resource estimate for the PEA update.  A National Instrument 43‐101 Technical Report (“the Technical Report”) will be filed on SEDAR within 45 days.

Note: The PEA is preliminary in nature and includes Inferred Mineral Resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves, and there is no certainty that the preliminary economic assessment will be realized.  Mineral Resources are not Mineral Reserves and do not have demonstrated economic viability.

A summary of the key financial information for the updated PEA is provided in Table 1.

Table 1.   PEA Summary 

Financial Summary – Base CasePre‐taxAfter‐tax
NPV (8% discount rate) IRR Payback periodUS$731.7 million 34.8% 2.4 yearsUS$433.5 million 25.9% 2.9 years
Pre‐production capital expenditure (Capex)1 Sustaining Capex Life of Mine (LOM) Capex C1 Cash Cost / Pound of Payable Zinc All‐in Sustaining Cost (AISC) / Pound of Payable Zinc Closure CostUS$382 million US$313 million US$695 million US$0.55 US$0.68 US$20 million

Notes: 1 Includes contingencies of US$76 million.

A summary of the Life of Mine (LOM) operating summary for the updated PEA is provided in Table 2. The after‐tax cash flow by year of production is presented in Figure 1.

Table 2.  LOM Operating Summary for the updated PEA with Metal Prices assumptions 

Operating SummaryValue
Operating days per year Processing plant throughput Zn/Ag/Pb Processing plant throughput Sn Average annual zinc concentrate production Average annual tin concentrate production Average annual lead‐silver concentrate production Average annual silver in lead concentrate Total LOM zinc in concentrate Net Smelter Return from zinc and lead concentrates Net Smelter Return from tin concentrate360 days/year 2.0 Mtpa 0.3 Mtpa 180,000 dmt/year 3,000 dmt/year 5,500 dmt/year 0.56 million oz/year 1.9 million tonnes US$4,000 million US$460 million
Mining costs (including backfill) Processing costs Zn/Ag/Pb Processing costs Sn Tailings G&A costs LOM Average Operating Cost (Zn/Ag/Pb) LOM Average Operating Cost (Sn)US$16.88/t US$11.00/t US$23.63/t US$0.94/t US$6.23/t US$35.06/t US$47.68/t

Notes:  dmt = dry metric tonne.

Numbers may not add due to rounding.

Base Case Metal Prices & Exchange Rate AssumptionsValue
Zinc Price Lead Price Silver Price Tin Price NSR Cut‐off value ‐ Zinc Zone and Silver Zone NSR Cut‐off value – Tin Zone Exchange Rate ‐ Peruvian SOL/USDUS$1.30/lb US$1.00/lb US$22/oz US$11.00/lb US$60/t US$80/t 3.70
Total LOM tonnage processed45.55 million tonnes
Mine Life Zn/Ag/Pb Mine Life Sn21 years 15 years

Figure 1.  Ayawilca 2024 PEA – After‐Tax Cash Flow by Year of Production (in US$) 

Mining 

The Ayawilca Project is planned as an underground mine operation.  For the purposes of the PEA, the Zinc Zone (together with the Silver Zone) will be mined at a rate of 2.0 Mtpa, whilst the Tin Zone will be mined at a rate of 0.3 Mtpa.  Mining of both zinc and tin zones commence together with each feeding separate processing plants.  The LOM is 21 years for the Zinc Zone and 15 years for the Tin Zone.  Mining in the Zinc and Tin Zones will utilize a long hole open stoping (“LHOS”) method in a transverse direction with level spacing ranging from 15 to 20 m.  The Silver Zone uses LHOS in a longitudinal direction at a 20 m level spacing. A top‐down overhand mining sequence is applied, working on top of paste‐fill between sill pillars which are recovered.  Three declines are planned from surface, initially two declines to access the South, Silver, and West areas and in later years the Central and East areas will be accessed by a third decline. The Tin Zones are also accessed through these planned declines.

Production is assumed to commence following 18 months of construction and commissioning.  The mine plan for the Zinc and Silver Zones is based on mining a total of 41.2 million tonnes grading 5.02% Zn, 17.3 g/t silver and 0.19% lead over a 21‐year LOM using an NSR cut‐off of US$60/t.  The Tin Zone is based on mining a total of 4.32 million tonnes grading 0.92% tin over a 15‐year LOM using an NSR cut‐off of US$80.  The mill feed will be trucked to the surface via multiple ramp systems connecting the three mine portals to the underground infrastructure and accessing production areas starting at the South and West areas of the Zinc Zone, the Silver Zone, and the high recovery area of the Tin Zone (see Figures 2 and 3).

Figure  2.    Mining Schedule for Zinc‐Silver‐Lead Plant (left) and Tin Plant (right) showing Average Grades by Year 

Figure  3.     Oblique view of Ayawilca mine design and stopes showing LOM Schedule  

Metallurgy and Processing 

Processing of the zinc‐rich mineralization will be through a conventional crushing and grinding circuit followed by froth flotation, concentrate thickening and filtration.  Metallurgical test work indicates a zinc concentrate grading 50% zinc can be produced from Zinc and Silver Zones with 92% of the zinc in the Zinc Zone recovered to the zinc concentrate (see news release of June 5, 2019), and 87% of the zinc in the Silver Zone recovered to the zinc concentrate.  The lead concentrate  is  expected  to  contain  47%  lead  and  average  3,140  g/t  silver  over  the  LOM.  Based  on  preliminary metallurgical test work, 45% of the silver in the Zinc Zone is expected to report to the lead concentrate and be payable, while 40% of the silver is expected to report to the zinc concentrate and not be payable.  In the Silver Zone, 85% of the silver (and 85% of the lead) is expected to report as a credit to a commercial lead concentrate. The zinc concentrate is expected to be a marketable concentrate with no deleterious elements other than an iron penalty.  Concentrate grade assumptions and recoveries for the principal metals in the Zinc and Silver Zones are summarized in Table 3 below.

Table 3.   LOM Head Grades and Metallurgical Recoveries for the Zinc‐Silver‐Lead Circuit 

ProductZinc/Silver‐Lead Concentrates Average Grade LOMMetallurgical Recoveries (%)1
Zinc (%)Lead (%)Silver (g/t)Av. NSR (US$/t)ZincLeadSilver
Feed grade Zinc Concentrate Lead Concentrate5.02 50.0 4.00.19 0 to 0.1 4717.3 0‐100 3,14029992/87 00 70/8540/0 45/85

1 First number relates to recovery in Zinc Zone and second number to Silver Zone 2 Silver concentrate grades were calculated for the PEA and range from 897 to 5,849 g/t

The first 200,000 wmt/a of zinc concentrates are assumed to be delivered directly to a local refinery (around 90% of LOM production); the balance is assumed to be sold to refineries in east Asia. The zinc concentrate also contains high indium (around 650 ppm In) and receives a US$20/dmt credit in concentrate shipped to Asia. All of the silver‐lead concentrates are assumed to be sold overseas. Off‐site charges include transport costs, treatment charges, refining charges, and iron penalties at refinery are summarized below in Table 4.

Table 4.   LOM Head Grade and Metallurgical Recovery for the Tin Circuit 

ProductAverage Grade LOMMetallurgical Recoveries (%)
Tin (%)Av. NSR (US$/t)Tin – CoarseTin – Fine
Feed grade Tin Concentrate0.92 50.01069050

Initial metallurgical testwork indicates that a tin concentrate grading 50% with 90% recovery can be produced from the high recovery (i.e., coarse tin) part of the Tin Zone, and a tin concentrate grading 50% with 50% recovery can be produced from the lower recovery (i.e., fine tin) part of the Tin Zone. The coarse tin represents 19% of the overall tin feed. The tin concentrates are anticipated to have markets in Asia and therefore all of the tin concentrate produced is assumed to be shipped overseas. Off‐site charges include transport, treatment charges, refining charges, and penalties at refinery and summarized below in Table 5.

Table 5.   Off‐Site Charges 

DescriptionZinc ConcentrateSilver‐Lead ConcentrateTin Concentrate
Transport to Port/Local refinery Port Charges Shipping to overseas smelter (FOB) Local refinery Treatment Charge (TC) Overseas Treatment Charge (TC) Ag Refining Charge (RC) Indium Credit (Overseas only) Sulphur Penalty Iron PenaltyUS$40/wmt US$25/wmt US$45/wmt US$220/dmt US$220/dmt ‐ US$20.00/dmt US$7.50/dmtUS$40/wmt US$50/wmt US$15/wmt ‐ US$50/dmt US$0.80/oz ‐US$40/wmt US$50/wmt US$15/wmt ‐ US$750/dmt ‐ ‐ US$75/dmt 0.7 units

Notes:  wmt = wet metric tonne.  dmt = dry metric tonne

For silver‐lead concentrates grading less than 2,500 g/t Ag, treatment charge is $150/dmt and refining charge is $1.00/oz Ag.

Approximately 60% of the tailings will be thickened and filtered for dry stack tailings disposal.  The remaining 40% will be prepared as pastefill and reticulated to the underground mine to be used as structural backfill.

Infrastructure 

Access  There is a good existing road network from the Project to the coast of Peru.  The Project lies approximately 250 km from the Port of Callao and a zinc refinery.  The road leaving the Project is an all‐weather gravel road that crosses the high central Andes for about 60 km before joining a bitumen road to the coast and then to the Port of Callao via the Pan‐American highway.  The Cajamarquilla zinc refinery is situated on the eastern outskirts of the city of Lima with good access from the highway.

Tailings and Mine Waste Management  The tailings and mine waste concept for the Ayawilca PEA is based on a commitment to implementing best available practices and best available technologies, as described in the International Council of Mining and Metals (“ICMM”) Global Industry Standard for Tailings Management.  The location of the TSF has been selected to minimize any potential risks for downstream areas. It is envisaged that:

  • 100% of mine waste rock and 40% of tailings production will be re‐used as underground mine backfill;
  • On‐surface tailings will be processed as filtered tailings and stacked at a secure and prepared facility. This method  will  reduce  the  environmental  footprint  and  the  risk  of  failure  and  the  attendant  environmental impacts, while also minimizing water consumption.
  • The filtered tailings facility has been located adjacent to the process plant area, minimizing the haul distance for the tailings and reducing environmental and social impacts.

Power  A new electricity substation is currently under construction 4.7 km from Ayawilca by a 3rd party mining company.  The Project will include construction of a transmission line from this substation to a substation at Ayawilca.  Tinka has recently received approval of a pre‐operation environmental study (“EPO”) to access 220kV / 23 MW power supply through a substation at Ayawilca.  Ayawilca is now planned to become connected to the national electrical grid.

Capital and Operating Costs 

The major components of the initial capital expenditure of US$$382 million include US$89.4 million for the zinc‐silver‐ lead processing plant, US$29.0 million for the tin processing plant, US$34.0 million for on‐site infrastructure, US$56.6 million for mine equipment and underground pre‐production development, US$17.8 million for site preparation of the filtered tailings storage facility and related mobile equipment, $15.5 million for the pastefill plant, $52.4 million for other surface facilities, and US$45.0 million other costs including indirects and owners costs.  Contingency in the initial capital  totals  US$76.2million.    Total  sustaining  capital  is  $313.1  million  over  the  21‐year  mine  life.  The  major components  of  sustaining  capital  are  US$176.3  million  for  mining  equipment  (including  major  components  and rebuilds) and materials handling, $49.8 million for mine development, ventilation and water management, US$46.0 million for tailings management. Contingency in sustaining capital totals US$40.8 million.

The estimated capital costs, over the life of the Project, are as follows in Table 6.

Table 6.   Capital Costs Summary 

Capital Cost ItemInitial (US$ M)Sustaining (US$ M)LOM Total (US$ M)
Mining & mine development Process plant – Zn/Ag/Pb Process plant ‐ Sn Pastefill plant Tailings Other surface facilities Subtotal Other indirects Owner’s costs Contingency56.6 89.4 29.0 15.5 17.8 52.4 261.7 34.7 10.3 76.2226.3 ‐ ‐ ‐ 46.0 ‐ 272.2 ‐ ‐ 40.8282.9 89.4 29.0 15.5 63.7 52.4 534.0 34.7 10.3 117.0
TOTAL PROJECT (US$ M)381.8313.1694.9
CLOSURE COSTS (US$ M)19.5

Numbers may not add due to rounding

The estimated operating costs, over the life of the Project, are as follows in Table 7.

Table 7.   Operating Costs per Mining Method for the Zinc and Tin Plants 

US$/t Processed
Operating Cost ItemZinc PlantTin PlantWeighted Average Zinc + Tin
Mining Backfill Sub‐total Processing Tailings G&A13.15 3.73 16.88 11.00 0.94 6.2313.15 3.73 16.88 23.63 0.94 6.2313.15 3.72 16.88 12.20 0.94 6.23
TOTAL PROJECT35.0647.6836.25

Sensitivities 

The Ayawilca project is strongly leveraged to zinc and to a lesser extent tin and silver prices.  A 25% increase on the base case zinc price (from US$1.30 to US$1.625) results in an after‐tax NPV8% of US$741 million.  A 25% increase on the base case tin price (from US$11.00 to US$13.75) results in an after‐tax NPV8% of $472 million.  See Figure 4.

Figure 4. PEA Sensitivities for Metals Prices, Operating Cost and LOM Capital Costs 

Opportunities and Exploration Potential 

The Ayawilca deposit has not been fully delineated by exploration drilling, and several of the zones remain open along strike and at depth.  Opportunities for additional value at Ayawilca not captured in the PEA include, but not limited to:

1. Potential to extend the Zinc Zone deposits to depth at the East and West areas with more drilling;

2. Potential to extend the Tin Zone to depth at the Central area, in particular where a steeply‐dipping feeder zone is interpreted and is untested by drilling;

3. Potential to extend the Silver Zone along strike and at depth – only 500 m of strike length is tested to date;

4. Optimization  of  zinc  recovery  to  a  zinc  concentrate  (currently  92%)  and  silver  recovery  to  a  silver‐lead concentrate in the Zinc Zone (currently 45%) with more detailed metallurgical test work;

5. Optimization of tin recovery to a tin concentrate from the low recovery domain (currently 50%) with more detailed metallurgical testwork.

Mineral Resource Estimation  

The updated Ayawilca Project Mineral Resource estimate for the Zinc Zone, Silver Zone, and Tin Zone is summarized in Table 8, Table 9, and Table 10, respectively, as estimated by SLR Consulting (Canada) Ltd (SLR).  For the purposes of demonstrating ‘Reasonable Prospects for Eventual Economic Extraction’ (RPEEE), Mineral Resources are constrained within underground reporting shapes generated in Deswik Stope Optimizer (“DSO”) using a minimum mining width of three metres and an NSR cut‐off value of $50/t for the Zinc and Silver Zones and $60/t for the Tin Zone.  Canadian Institute  of  Mining,  Metallurgy  and  Petroleum  (“CIM”)  Definition  Standards  for  Mineral  Resources  and  Mineral Reserves dated May 10, 2014 (“CIM (2014)” definitions) are used for classification of Mineral Resources. The Tin Zone, Zinc Zone and Silver Zone resources do not overlap.

To satisfy RPEEE for an underground mining scenario, Tinka is reporting Mineral Resources within potentially mineable shapes  (i.e.,  stopes)  thereby  demonstrating  the  spatial  continuity  of  the  mineralization.    Where  the  potentially mineable volumes (i.e., stopes) contain smaller zones of mineralization with values below the stated cut‐off, this lower grade material is included in the Mineral Resource estimate.

The updated Mineral Resources estimate as at January 1st, 2024, contains the following:

  • Indicated Zinc Zone Mineral Resource of 28.3 Mt grading 5.82% zinc, 16.4 g/t silver, 0.2% lead & 91 g/t indium containing:
    • 3.64 billion pounds of zinc;
    • 14.9 million ounces of silver;
    • 108 million pounds of lead; and
    • 2,582 tonnes of indium.
  • Inferred Zinc Zone Mineral Resource of 31.2 Mt grading 4.21% zinc, 14.5 g/t silver, 0.2% lead & 45 g/t indium containing:
    • 2.90 billion pounds of zinc;
    • 14.6 million ounces of silver;
    • 133 million pounds of lead; and
    • 1,414 tonnes of indium.
  • Inferred Silver Zone Mineral Resource of 1.0 Mt grading 111.4 g/t silver, 1.54% zinc, & 0.5% lead containing:
    • 3.7 million ounces of silver;
    • 35 million pounds of zinc; and
    • 12 million pounds of lead.
  • Indicated Tin Zone Mineral Resource of 1.4 million tonnes grading 0.72% tin, containing:
    • 22 million pounds of tin.
  • Inferred Tin Mineral Resource of 12.7 million tonnes grading 0.76% tin, containing:
    • 213 million pounds of tin.

No Mineral Reserves have been estimated at the Project.

The Zinc, Silver, and Tin Zone Mineral Resource estimates for the Ayawilca Project were updated by SLR using the drill results available to May 31, 2023.  The deposit drill database includes 249 drill holes totalling 94,258 m.  An additional 35 drill holes totalling 12,216 m have been added since the previous update dated August 30, 2021.  Three‐dimensional (3D) wireframe models were generated using an approximate NSR cut‐off value of $40/t for the Zinc Zone.  For the Tin Zone, a 0.2% Sn or NSR cut‐off value of $30/t was used for wireframe models.  Prior to compositing to two metre lengths, high tin, silver, and lead values were capped for each zone individually. Zinc, silver, lead, tin, and indium high grade outliers were constrained during interpolation on a per domain basis.  Block model grades within the wireframe models were interpolated by inverse distance cubed (ID3).  Despite lead grades generally being low, it is assumed that lead and silver will be recovered in a lead concentrate.  Density was assigned to blocks within the resource wireframes by ID3.  Where density sample data was insufficient for interpolation, density values were derived from a regression equation based on the iron value of the block.  Figures 5 and 6 show the Mineral Resource wireframes in plan and 3D views.  Cross sections of the resource wireframes are shown in Figures 7 and 8.

The Mineral Resources were classified following CIM (2014) definitions as Indicated and Inferred using drill hole spacing based criterion, mineralization continuity, and thickness.  The drill hole spacing within a resource area assigned the Indicated category commonly ranges from 40 m to 70 m.

Table 8.  Ayawilca Zinc Zone Mineral Resources as of January 1, 2024 

Classification/ ZoneTonnage MtNSR $/tGradeContained Metal
Zn %Ag g/tPb %In g/tMlb ZnMoz AgMlb Pbt In
Indicated
South13.81286.6419.30.21202,0208.6521,655
West14.5985.0513.60.2641,6186.356927
Total Indicated28.31135.8216.40.2913,63814.91082,582
Inferred
South4.8793.8124.20.2344063.819163
West3.8894.6112.10.1613841.512229
Central9.1854.3910.60.2548783.147486
East13.5814.1314.40.2401,2296.355536
Total Inferred31.2834.2114.50.2452,89814.61331,414

Notes:

1. CIM (2014) definitions were followed for Mineral Resources.

2. The Mineral Resources have been reported within underground reporting shapes generated with Deswik Stope Optimizer (DSO) using a net smelter return (NSR) cut‐off value of US$50/t.  For the Central area, Mineral Resources were reported only within underground reporting shapes that also had a Zn grade above 3%.

3. NSR value was based on estimated metallurgical recoveries, assumed metal prices, and smelter terms, which include payable factors, treatment charges, penalties, and refining charges.  The NSR used for reporting is based on the following:

a. Long term metal prices of US$1.40/lb Zn, US$25/oz Ag, and US$1.10/lb Pb.

b. Net metallurgical recoveries of 92% Zn, 45% Ag, and 70% Pb.

4. The NSR value for each block was calculated using the following NSR factors: US$18.04 per % Zn, US$0.33 per gram Ag, and US$11.92 per % Pb.

5. The NSR value was calculated using the following formula: NSR = Zn(%)*US$18.04+Ag(g/t)*US$0.33+Pb(%)*US$11.92.

6. Bulk densities were assigned to blocks by interpolation and remaining blocks by regression of Fe assay data or average sample data. Averages range between 3.20 t/m3 and 3.51 t/m3.

7. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

8. Numbers may not add due to rounding.

Table 9.  Ayawilca Silver Zone Mineral Resources as of January 1, 2024 

ClassificationTonnage MtNSR $/tGradeContained Metal
Zn %Ag g/tPb %In g/tMlb ZnMoz AgMlb Pbt In
Inferred1.01001.54111.40.53353.7123

Notes:

1. CIM (2014) definitions were followed for Mineral Resources.

2. The Mineral Resources have been reported within underground reporting shapes generated with Deswik Stope Optimizer (DSO) using a net smelter return (NSR) cut‐off value of US$50/t.

3. NSR value was based on estimated metallurgical recoveries, assumed metal prices, and smelter terms, which include payable factors, treatment charges, penalties, and refining charges.  The NSR used for reporting is based on the following:

a. Long term metal prices of US$1.40/lb Zn, US$25/oz Ag, and US$1.10/lb Pb.

b. Net metallurgical recoveries of 77% Zn, 85% Ag, and 85% Pb.

4. The NSR value for each block was calculated using the following NSR factors: US$15.10 per % Zn, US$0.62 per gram Ag, and US$14.48 per % Pb.

5. The NSR value was calculated using the following formula: NSR = Zn(%)*US$15.10+Ag(g/t)*US$0.62+Pb(%)*US$14.48.

6. Bulk densities were assigned to blocks by interpolation and remaining blocks by regression of Fe assay data or average sample data. The average bulk density is 3.18 t/m3.

7. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

8. Numbers may not add due to rounding.

Table 10:  Ayawilca Tin Zone Mineral Resources as of January 1, 2024 

ClassificationTonnage MtNSR $/tGrade Sn %Contained Metal Mlb Sn
Indicated1.4990.7222
Inferred12.71040.76213

Notes:

1. CIM (2014) definitions were followed for Mineral Resources.

2. The Mineral Resources have been reported within underground reporting shapes generated with Deswik Stope Optimizer (DSO) using a net smelter return (NSR) cut‐off value of US$60/t.

3. The NSR value was based on estimated metallurgical recoveries, assumed metal prices, and smelter terms, which include payable factors, treatment charges, penalties, and refining charges.  Metal price assumption is US$12.00/lb Sn.  Metal recovery assumption is 64% Sn.  The NSR value for each block was calculated using the following NSR factor: US$137.30 per % Sn.

4. The NSR value was calculated using the following formula: US$NSR = Sn(%)*US$137.30.

5. Bulk densities were assigned to blocks by interpolation and remaining blocks by regression of Fe assay data or average domain sample data.  The average bulk density is 3.65 t/m3.

6. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

7. Numbers may not add due to rounding.

Density 

A total of 4,226 density measurements are located within the wireframe models. This represents a nearly five‐fold increase  in  the  number  of  density  measurements  available  when  compared  to  the  previous  estimate.  A  linear regression established between core density data and iron assays was used to assign a density value to resource blocks that were not interpolated.  Linear regression equations were established for each area separately.  Overall, the density values in the updated 2024 mineral resource estimate have decreased by around 5% over the 2021 estimate.

In the previous estimate, density values were assigned to all blocks in each area based on the average density sample value after removing outliers.  In SLR’s opinion, density values were slightly overestimated in the previous estimate and the updated estimation methodology is more rigorous and better reflects local variations within the resource domains. SLR notes, however, that using a regression equation based on iron is not without flaws.  These include:

  • Overlimit iron assays will underestimate the iron content and low bias the density.
  • There is a negative correlation with high zinc and iron values, i.e., there is a potential to low bias Zn‐rich areas.

A small proportion of blocks within the South and West areas are assigned a density value using the iron regression equation.  Within the Central area, however, approximately 50% of blocks are assigned a density value using the iron regression equation and within the East area, there are not enough samples to establish a correlation between density and iron.