SAGA Metals Reports Assays from R-0044 to R-0046 with Intercepts Including 58.33% Fe₂O₃, 8.78% TiO₂, 0.415% V₂O₅ from 2026 Drilling at Trapper South, Radar Critical Minerals Project in Labrador
VANCOUVER, B.C. – June 11, 2026 – SAGA Metals Corp. ("SAGA" or the "Company") (TSXV: SAGA) (OTCQB: SAGMF) (FSE: 20H), a North American exploration company focused on critical mineral discoveries, is pleased to report additional assay results from drill holes R-0044, -0045 and -0046 completed in 2026 as part of its ongoing maiden Mineral Resource Estimate ("MRE") diamond drill program at the Trapper Zone within the 100%-owned Radar Titanium-Vanadium-Iron Project near Cartwright, Labrador, Canada.
The Trapper Zone forms part of an oxide corridor that includes the Falcon and Hawkeye Zones spanning 29 square kilometres near the center of the Property.
Figure 1: The Radar Property with the Dias QMAGT vertical gradient (Bzz) anomaly footprint shown in red (high-amplitude pixels only). The QMAGT-imaged central oxide-layering corridor validated over 29 km2, encompassing the Trapper Zone, Hawkeye Zone, and the new Falcon Zone.
Trapper South Assay Highlights
- Analytical results received for three (3) additional diamond drill holes (R-0044 to R-0046) from the MRE drill program initiated in Q4 2025, delivering consistent broad intercepts of oxide mineralization.
- Key intercepts include:
- Hole R-0044: 22.9 m @ 51.38% Fe₂O₃, 6.85% TiO₂, 0.416% V₂O₅
- Hole R-0045: 71.3 m @ 48.28% Fe₂O₃, 6.21% TiO₂, 0.373% V₂O₅ Including 40.0 m @ 53.69% Fe₂O₃, 7.32% TiO₂, 0.441% V₂O₅
- Hole R-0046: 127.9 m @ 52.94% Fe₂O₃, 7.35% TiO₂, 0.388% V₂O₅
- Including 54.0 m @ 58.33% Fe₂O₃, 8.78% TiO₂, 0.415% V₂O₅
- Including 65.1 m @ 43.84% Fe₂O₃, 5.90% TiO₂, 0.316% V₂O₅
- Including 20.6 m @ 54.21% Fe₂O₃, 7.46% TiO₂, 0.426% V₂O₅
• These results now bring the total MRE drill results to thirty-nine (39) diamond drill holes received to date. As reported previously, analytical results from the first thirty-six (36) diamond drill holes of the MRE drill program include:
| DDH | FROM | TO | Length | True Thickness | Fe2O3 | TiO2 | V205 |
|---|---|---|---|---|---|---|---|
| ID | m | m | m | m | % | % | % |
| R-0008 | 170.0 | 237.6 | 68.3 | 66.2 | 46.15 | 9.21 | 0.311 |
| R-0009 | 94.0 | 181.2 | 87.2 | 84.4 | 50.67 | 10.15 | 0.339 |
| R-0010 | 1.5 | 137.0 | 135.5 | 121.7 | 50.03 | 7.87 | 0.352 |
| R-0011 | 58.1 | 153.3 | 95.2 | 50.8 | 39.49 | 6.49 | 0.222 |
| R-0012 | 3.8 | 79.0 | 75.2 | 39.6 | 27.39 | 4.87 | 0.116 |
| R-0013 | 9.5 | 121.0 | 111.5 | 97.9 | 37.08 | 5.14 | 0.242 |
| R-0014 | 8.8 | 50.0 | 41.2 | 14.9 | 36.17 | 6.36 | 0.188 |
| R-0015 | 73.3 | 174.0 | 100.7 | 88.9 | 38.56 | 6.80 | 0.229 |
| R-0016 | 44.0 | 94.6 | 50.6 | 47.1 | 52.05 | 7.21 | 0.375 |
| R-0017 | 50.6 | 140.6 | 90.0 | 73.0 | 51.86 | 6.76 | 0.417 |
| R-0018 | 44.7 | 115.0 | 70.3 | 44.1 | 42.64 | 5.66 | 0.288 |
| R-0019 | 66.6 | 112.3 | 45.7 | 41.6 | 49.51 | 6.56 | 0.374 |
| R-0020 | 87.3 | 128.0 | 40.7 | 31.1 | 37.62 | 4.93 | 0.239 |
| R-0021 | 96.0 | 127.4 | 31.4 | 16.5 | 53.18 | 7.08 | 0.414 |
| R-0022 | 62.0 | 92.6 | 30.6 | 28.6 | 49.4 | 6.61 | 0.373 |
| R-0023 | 100.5 | 186.5 | 86.0 | 54.0 | 45.5 | 5.5 | 0.367 |
| R-0024 | 112.0 | 203.0 | 91.0 | 58.7 | 49.08 | 6.23 | 0.39 |
| R-0024 | 142.0 | 186.0 | 44.0 | 28.4 | 54.2 | 7.07 | 0.443 |
| R-0025 | 141.3 | 223.0 | 81.7 | 58.5 | 41.36 | 5.18 | 0.309 |
| R-0025 | 168.0 | 201.0 | 33.0 | 23.7 | 47.38 | 6.01 | 0.384 |
| R-0026 | 141.7 | 189.0 | 47.3 | 27.7 | 38.16 | 4.65 | 0.288 |
| R-0026 | 110.9 | 131.4 | 20.5 | 12.0 | 52.39 | 6.55 | 0.449 |
| R-0027 | 81.2 | 162.0 | 80.8 | 63.4 | 42.74 | 5.18 | 0.320 |
| R-0028 | 105.7 | 211.0 | 105.3 | 54.5 | 42.39 | 5.40 | 0.306 |
| R-0028 | 144.0 | 182.0 | 38.0 | 19.7 | 49.43 | 6.50 | 0.382 |
| R-0029 | 65.2 | 172.0 | 106.8 | 95.5 | 44.41 | 5.36 | 0.341 |
| R-0029 | 65.2 | 104.0 | 38.8 | 34.7 | 53.02 | 6.46 | 0.441 |
| R-0030 | 83.1 | 174.0 | 90.9 | 49.5 | 42.57 | 5.40 | 0.303 |
| R-0030 | 83.1 | 101.7 | 18.6 | 10.2 | 50.81 | 6.56 | 0.398 |
| R-0031 | 63.4 | 171.6 | 108.2 | 87.2 | 38.11 | 5.13 | 0.254 |
| R-0031 | 97.0 | 140.1 | 43.1 | 34.7 | 42.71 | 5.88 | 0.309 |
| R-0032 | 53.8 | 198.0 | 144.2 | 135.3 | 37.13 | 5.04 | 0.234 |
| R-0032 | 114.0 | 170.0 | 56.0 | 52.6 | 44.68 | 6.50 | 0.294 |
| R-0033 | 67.4 | 168.0 | 100.6 | 77.5 | 44.07 | 6.38 | 0.286 |
| R-0033 | 97.0 | 153.0 | 56.0 | 43.1 | 48.03 | 7.25 | 0.304 |
| R-0034 | 68.8 | 195.0 | 126.2 | 124.0 | 43.19 | 6.05 | 0.293 |
| R-0034 | 106.1 | 170.0 | 63.9 | 62.8 | 48.61 | 7.01 | 0.344 |
| R-0035 | 8.5 | 22.0 | 13.5 | 9.9 | 30.98 | 2.93 | 0.193 |
| R-0036 | 55.0 | 128.0 | 73.0 | 36.5 | 45.34 | 6.31 | 0.345 |
| R-0036 | 80.0 | 114.0 | 34.0 | 17.0 | 50.46 | 7.21 | 0.395 |
| R-0037 | 52.2 | 103.0 | 50.8 | 41.9 | 45.93 | 6.46 | 0.348 |
| R-0038 | 45.4 | 146.2 | 100.8 | 73.7 | 41.23 | 5.21 | 0.302 |
| R-0038 | 103.9 | 146.2 | 42.4 | 31.0 | 46.20 | 6.35 | 0.364 |
| R-0039 | 84.0 | 194.0 | 110.1 | 106.5 | 47.42 | 5.95 | 0.354 |
| R-0039 | 97.0 | 149.1 | 52.1 | 50.4 | 58.15 | 7.68 | 0.459 |
| R-0039 | 166.4 | 194.0 | 27.6 | 26.7 | 45.88 | 5.85 | 0.350 |
| R-0040 | 84.9 | 130.0 | 45.1 | 31.9 | 51.20 | 7.94 | 0.340 |
| R-0041 | 6.6 | 53.0 | 46.4 | 34.7 | 47.97 | 6.49 | 0.368 |
| R-0042 | 102.1 | 137.4 | 35.3 | 23.6 | 50.68 | 6.74 | 0.378 |
| R-0043 | 28.4 | 68.2 | 39.8 | 30.4 | 47.93 | 7.24 | 0.307 |
Table 1: MRE drill program assay intercepts previously reported in Q4 2025 and 2026 to date from drill holes R-0008 to R-0043.
- Top 15 intercepts from the MRE Drill Program to date can be found in Table 4 below.
- Completed fifty (50) holes (R-0008 to R-0057) from Q4 2025 to date in 2026, with significant oxide intercepts including 202.3 m from R-0053 (true thickness of 132.1) of semi-massive oxide with extensive rhythmic oxide layering.
- MRE drilling to date has returned multiple holes of thick oxide core intercepts exceeding 70– 144 metres and certain assay intervals frequently above 45–58% Fe₂O₃, 6–8% TiO₂ and 0.37- 0.44% V₂O₅.
Rhythmic banding and semi-massive to massive oxide mineralization are observed • consistently in Trapper South, aligning with prior high-grade results from Trapper North.
- Drilling is progressing efficiently, with 11,600 m completed in the Trapper Zone to date.
- Confirmed 29 km2 central oxide corridor
- Excellent core recovery and representative sampling support ongoing metallurgical test work and the advancement of the maiden Mineral Resource Estimate.
Michael Garagan, CGO & Director of SAGA Metals, commented:
“These latest results from holes R-0044 through R-0046 continue to demonstrate the impressive scale and continuity of the oxide system at Trapper South. Hole R-0046 in particular was a standout, stretching a full 490.1 m (over 1,600 feet) and reaching 280 m vertical depth while returning broad zones of strong oxide mineralization, including over 100 m of higher-grade material averaging 7.35% TiO₂ and 0.388% V₂O₅.
Holes R-0044 and R-0045 further reinforce the consistency we’re seeing across the Trapper Zone, with thick intercepts of rhythmic oxide layering and semi-massive mineralization. The ability to repeatedly intersect wide zones of oxide mineralization with high grades across multiple sections speaks to the robustness of this system. These results continue to build our confidence as we advance toward a maiden Mineral Resource Estimate at Radar.”
2026 Trapper South Drilling Summary
Table 2: Summary of drill holes R-0016 to R-0057, highlighting the oxide intercepts. See Figures 3-4 below, which depict the oxide mineralization in cross sections S6 and S8. True thickness represents the perpendicular width of the mineralized zone, while the total downhole oxide represents the length of the mineralization intercepted downhole.
| Total Meters Drilled | Total Samples | |
|---|---|---|
| Trapper South 2025 | 2050 | 1313 |
| Trapper South 2026 | 9550 | 5719 |
| Trapper Total | 11600 | 7032 |
Table 3: Summary of total meters drilled in Q4 2025 and 2026 to date, including total core samples cut and prepared.
Figure 2: Trapper South map outlining location of the initial 2026 focus for the remainder of the MRE drill program to be completed in 2026, including cross-sections S14, S13, S12, S11, S10, S9, S8, S7, S6, S5, and S4, showing the TMI of the 2025 Trapper Zone ground magnetic survey.
The latest results from these drill holes, R-0044, R-0045 and R-0046, once again demonstrate excellent continuity across broad zones of oxide mineralization, underscoring the growing potential for a sizable mineral resource that could create meaningful long-term value for SAGA shareholders.
Detailed Logging Highlights from Drill Hole R-0044 to R-0046
- Hole R-0044 (Cross-Section S06): Drill hole R-0044 is drilled on cross-section S6, with an azimuth of 218 and a dip of -45°, with a total depth of 167 m. The oxide zone is 22.9m thick, intersected at 82.85m, at a sheared felsic dyke marking the contact between gabbronorite and semi-massive oxide. Oxide zone includes rhythmic oxide layering (3.7 m) and semimassive oxide (19.3 m) ending at 105.8 m.
• Hole R-0045 (Cross-Section S08): Drill hole R-0045 is drilled on cross-section S8, with an azimuth of 218 and a dip of -45° with a total depth of 245 m. The oxide zone is 139.2 m thick, intersected at 39.3 m at a sharp contact from gabbronorite to rhythmic banding. Semimassive oxide starts at a faulted lower contact of a felsic dyke at 76.8 m. Oxide zone includes rhythmic oxide layering (71.7 m) and semi-massive oxide (67.4 m). The oxide zone ends at 223.6 m at a sharp contact from rhythmic banding to gabbronorite.
• Hole R-0046 (Cross-Section S08): Drill hole R-0046 is drilled on cross-section S8, with an azimuth of 218 and a dip of -45°, with a total depth of 491 m. This hole tests both of the magnetic anomalies in Trapper South. The first oxide zone is 140.5 m thick and is intersected at 7.4 m at a sharp contact of gabbronorite and rhythmic layering. This zone includes rhythmic oxide layering (18.7 m) and semi-massive oxide (121.8 m). The oxide zone ends at 147.9 m at a faulted contact of a felsic dyke.
The second oxide zone is 198.2 m thick and is intersected at 237.7 m at a fault contact from gabbronorite to rhythmic banding. This zone includes rhythmic oxide layering (176.7 m) and semi-massive oxide (21.4 m). The oxide zone ends at 445.9 m at a sharp contact from rhythmic banding to gabbronorite.
An intermediate zone (147.9 m to 237.7 m) with 39.0 m of rhythmic layering is observed from 176.6 m at a faulted contact of felsic dyke and ending at 215.5 m. This intermediate zone between the two magnetic anomalies is faulted and hosts many felsic dykes.
Figure 3: Cross section of S6 looking NW showing R-0019, -0027, -0028, -0042, -0043, -0044 and -0047, highlighting intercepts of semi-massive oxides and layering sequence with the 3D Magnetic Inversion of the 2025 Trapper Zone ground magnetic survey. Assays shown for R-0019, R-0027, R-0028, R-0042, R-0043 and R-0044. Assays are pending for R-0047.
Figure 4: Cross section of S8 looking NW showing R-0016, -0017, -0023, -0026, -0035, -0045 and -0046, highlighting intercepts of semi-massive oxides and layering sequence with the 3D Magnetic Inversion of the 2025 Trapper Zone ground magnetic survey. Assays shown for R-0016, R-0017, R-0023, R-0026, R-0035, R- 0045 and R-0046.
Sampling Summary
Saga’s core cutting team finalized the cutting, sampling, and shipping of 450 samples from R-0047, -0048, and -0049. IGS Laboratories anticipates receiving the samples towards the beginning of next week. A total of 7,032 samples have been collected to date in the Trapper Zone.
Key Project Highlights
- Confirmed mineralization in 57 out of 57 drill holes completed and observed in two primary zones to date.
- Analytical results to date include numerous oxide-rich intercepts, including:
| DDH | FROM | TO | Length | True Thickness | Fe2O3 | TiO2 | V205 |
|---|---|---|---|---|---|---|---|
| ID | m | m | m | m | % | % | % |
| R-0009 | 94.0 | 181.2 | 87.2 | 84.4 | 50.67 | 10.15 | 0.339 |
| R-0008 | 170.0 | 237.6 | 68.3 | 66.2 | 46.15 | 9.21 | 0.311 |
| R-0046 | 20.0 | 74.0 | 54.0 | 43.7 | 58.33 | 8.78 | 0.415 |
| R-0040 | 84.9 | 130.0 | 45.1 | 31.9 | 51.20 | 7.94 | 0.340 |
| R-0010 | 1.5 | 137.0 | 135.5 | 121.7 | 50.03 | 7.87 | 0.352 |
| R-0039 | 97.0 | 149.1 | 52.1 | 50.4 | 58.15 | 7.68 | 0.459 |
| R-0017 | 73.0 | 140.6 | 67.6 | 54.9 | 55.13 | 7.37 | 0.448 |
| R-0045 | 104.0 | 144.0 | 40.0 | 31.1 | 53.69 | 7.32 | 0.441 |
| R-0033 | 97.0 | 153.0 | 56.0 | 43.1 | 48.03 | 7.25 | 0.304 |
| R-0043 | 28.4 | 68.2 | 39.8 | 30.4 | 47.93 | 7.24 | 0.307 |
| R-0016 | 44.0 | 94.6 | 50.6 | 47.1 | 52.05 | 7.21 | 0.375 |
| R-0036 | 80.0 | 114.0 | 34.0 | 17.0 | 50.46 | 7.21 | 0.395 |
| R-0021 | 96.0 | 127.4 | 31.4 | 16.5 | 53.18 | 7.08 | 0.414 |
| R-0024 | 142.0 | 186.0 | 44.0 | 28.4 | 54.20 | 7.07 | 0.443 |
| R-0034 | 106.1 | 170.0 | 63.9 | 62.8 | 48.61 | 7.01 | 0.344 |
Table 4: Top 15 intercepts from the 2025 & 2026 drilling programs at the Trapper Zone
- Infrastructure including road access, deep-water port, nearby hydro-electric power and regional airport.
- Confirmed a 29.0 km2 central oxide corridor that encompasses the Trapper, Falcon and Hawkeye Zones, demonstrating district-scale potential.
Consistent grades and thicknesses with semi-massive to massive oxide reporting up to •
72.33% Fe,13.3% TiO2, and 0.66% V2O5.
- Petrographic analysis confirms titanomagnetite mineralization is advantageous for
simplified metallurgical processing.
- A total of 11,600 m has been completed and reported to date for the MRE drill program. See Figure 2 showcasing 2026 drill hole locations in Trapper South reported to date.
About the Radar Critical Mineral Property in Labrador
The Radar Property comprises 690 mineral claims across 9 mineral licenses, totalling approximately 24,175 hectares in southeastern Labrador, located approximately 10 km south of Cartwright. The Property entirely encloses the Dykes River Intrusive Complex (~160 km² at the surface) and is accessible year-round via paved Route 510, a Cartwright logging road, and a SAGA-constructed access trail. Infrastructure advantages include the deep-water port at Cartwright, the Cartwright Airport (YRF), and proximity to regional hydroelectric power from Muskrat Falls and Churchill Falls.
Diamond drilling, geophysics, trenching and geological mapping have confirmed a 29 km2 oxide corridor encompassing the Trapper, Falcon and Hawkeye Zones. VTM mineralization at Radar is comparable to that of global Fe-Ti-V systems such as Panzhihua (China) and Bushveld (South Africa). Subject to further exploration, resource definition, and metallurgical testing, the Project may represent a strategic source of titanium, vanadium, and iron for North American markets.