Confederation Minerals Ltd. Announces Completion of the previously announced Preliminary Economic Assessment

Resource Estimates Economic Studies

Suite 1980, 1075 West Georgia Street, Vancouver, British Columbia, V6E 3C9 Tel: 604 688 9588; Fax: 778 329 9361

Confederation Minerals Ltd. Announces Completion of the previously announced Preliminary Economic Assessment

Vancouver,  B.C.;  Oct  23th,  2014;  Confederation  Minerals  Ltd.  (TSX.V:CFM;  OTCQX:CNRMF):  (“Confederation”  or  the  “Company”)  is  pleased  to  announce  the  completion  of  the  previously announced (April 8, 2013 press release) Preliminary Economic Assessment (PEA) for the Newman Todd Project ("the Project") in the Red Lake Mining District of Northern Ontario.

The Executive Summary of the full PEA, prepared by Mining Plus Canada Pty. (Mining Plus) from their Vancouver,  BC  offices,  will  be  available  shortly  on  the  Company’s  website (www.confederationmineralsltd.com) and on SEDAR (www.sedar.com). Furthermore, a technical report prepared in compliance (or accordance) with NI 43‐101 is being completed and will be available on the Company’s website and on SEDAR within 45 days.  The PEA was authored by Neil Schunke, MAusIMM (CP Mining) of Mining Plus Canada Consulting with contributions by Ralph Bullis, B.Sc., P.Geo, of Bullis Consulting,  Tracey  Meintjes,  P  Eng.  of  Moose  Mountain  Technical  Services,  Jeffrey  Barrett,  M.Sc.E., P.Eng of Stantec Consulting Ltd., Gary Giroux, MASc., P.Eng of Giroux Consultants Ltd, Andrea Diakow, B.Sc., P Geo, of Pamicon Developments Ltd. and Doug Blanchflower, B.Sc., P.Geo of Minorex Consulting Ltd.

The foremost purpose of this PEA is to provide early economic guidance to optimise future exploration efforts  along  the  extensive  gold‐bearing  hydrothermal  Newman  Todd  Structure  (NTS)  (see Confederation press releases over the preceding 24 months). Optimization scenarios contemplated in the report that could provide significant upside to the Newman Todd Project include:

  • Reduction of capital expenditure (processing plant, tailings storage facility and associated infrastructure) through toll treatment options
  • Expansion of land holding sufficient to construct processing plant, tailings storage facility and associated infrastructure adjacent to the Newman Todd operation instead of on claims 18km NE of the deposit
  • The Newman Todd Structure is open to extension to the northeast and southwest with several discrete known and untested targets and is also open at depth
  • Additional drilling may discover further high grade portions of the deposit along strike or down dip within the Newman Todd structure
  • Potential increase in resource quantity, particularly through further drilling of the near‐surface mineralised zones within the Newman Todd structure
  • Further constraining the high grade mineralization model within the deposit
  • Renegotiation and decrease of royalties.

Confederation’s CEO, Mr. Lawrence Dick, PhD., P, Geo. stated that “This PEA is an excellent tool to fine  tune our going‐forward exploration approach, to most efficiently and cost‐effectively explore the very  large Newman Todd gold‐bearing hydrothermal system.”

It should also be noted that the production by Confederation of a preliminary assessment (within the meaning  of  NI  43‐101),  along  with  the  issuance  to  Redstar  of  an  additional  500,000  shares  of Confederation, will exercise the second option in the Company’s option agreement with Redstar Gold Corp.  (TSX‐V:RGC)  thereby  increasing  Confederation’s  ownership  in  the  Newman  Todd   project  from 50% to 70% interest.

The  PEA  is  based  on  results  from  138  diamond  drill  holes  totalling  51,328  m  with  1,719  down  hole surveys and 45,300 assays for gold.  Drill holes tested the Newman‐Todd Structure (NTS) which accounts for most of the gold discovered to date on the Project.  The NTS stretches over the entire length of the Project property, a distance of about 1.8 kilometres, and is open outside of project boundaries.  Much of the  drilling  is  wide‐spaced  with  the  highest  drilling  density  in  the  “Hinge  Zone”  and  the  “Heath  Bull Zone” where drill centres are approximately 25 metres to a depth of about 300 metres.

Primarily as a result of distances between wide spaced drilling within the NTS, geostatistical restraints have limited the region of the NTS that contributes to the PEA to the Hinge Zone. It is anticipated that, given  the  large  scale  of  the  Project,  additional  drilling  in  the  NTS  will  add  to  the  resources  already identified for the PEA.

While the Company understands that the results of the PEA presented are, by definition, preliminary the Company sought guidance, through the PEA summarized below, to help determine parameters for future exploration of the much larger NTS system extending well outside the Hinge Zone and to a depth of at least 900m.

Stated Mr. Dick, “We have had unprecedented exploration success with gold intercepted on almost every  hole  along  the  1.8km  NTS,  including  a  consistent  trend  of  increased  grades  along  the  hanging  wall  contact. We have a small region in the Hinge Zone at the centre of the property where drill density and  grade are starting to contribute to something economically meaningful. Expanding this zone laterally  and to depth is our goal and we look forward to sequential positive updates to our existing model.”

Summary

The PEA is  based on the  resource  model  (with effective date  December 17, 2013),  extraction of the deposit  by  open  pit  mining  methods  and  additional  metallurgical  and  environmental  studies.    A  pit optimisation process (using Whittle software) was undertaken to identify the ultimate pit shell using the base case economic and geometric parameters. Project highlights and key potential economic outcomes from the mine plan considered in this PEA are detailed in Table 1.

TABLE 1
Mining
Mining Inventory tonnes, t1,157,727
Mining production rate, tpa375,000
Total open pit material mined, t7,487,665
Stripping ratio5.47
Production
Average feed grade Au, g/t2.5
Payable Au, oz82,699
Capital Costs
Initial Capital Costs, CA$M48.8
Sustaining Capital Costs, CA$M23.2
Mine Closure Capital Costs, CA$M5.1
Contingency (Initial Capital Costs), CA$M9.8
Contingency (Sustaining Capital Costs), CA$M2.1
Total Capital Costs, CA$M89.1
Operating Costs
Total Operating Costs, CA$M90.6
Unit Operating Costs, CA$/t milled78.3
Metal Price and Exchange Rate Assumptions
Au price, US$/oz1,400
USD/CAD exchange rate1.01
Economic Outcomes
Net income (pre-tax, undiscounted), CA$M(66.9)
Net Present Value (pre-tax, 5% discount rate), CA$M(62.4)

Note: All designs and costs in this Preliminary Economic Assessment are preliminary in nature and include both Indicated and Inferred Mineral Resources. Inferred Mineral Resources are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves.

Resources

The  mineral  resource  estimate  for  the  Newman  Todd  Project  was  prepared  by  Gary  Giroux,  MASc., P.Eng.,  of  Giroux  Consultants  Ltd,  using  higher  grade  quartz  carbonate  breccia  mineralized  shells outlined  and  provided  by  Ralph  Bullis,  B.Sc.,  P.Geo,  of  Bullis  Consulting  and  a  geologic  solid  model provided by Doug Blanchflower, B.Sc., P.Geo of Minorex Consulting Ltd.  Andrea Diakow, B.Sc., P Geo, of Pamicon  Developments  Ltd  provided  data  verification  through  quality  assurance  and  quality  control protocols in the drilling assays and field sampling on the project. Other geological data was supplied by Confederation  Minerals  Ltd.  The  higher  grade  shells  were  used  to  create  3D  wireframes  for  ten mineralised  zones  that  were  subsequently  used  to  constrain  the  mineralised  breccia  zones.  A  3D wireframe representing the Newman Todd Structure was also created and will be included in our web site subsequent to the publication of this news release. Resources are classified according to NI43‐101 and CIM Definition Standards based on the geologic continuity established through surface mapping and drill  hole  interpretation.    The  Mineral  Resources  at  a  0.7  g/t  Au  cutoff  for  Newman  Todd  are  as summarised in Table 2.  Table 3 presents the Newman Todd Mineral Resource Estimate at a range of cut‐off grades.

Table 2 Newman Todd Mineral Resource Estimate 

Resource ClassTonnesAu Grade (g/t)Au Ounces
Total Indicated Resources6,400,0001.35277,000
Total Inferred Resources7,630,0001.35332,000

Table 3 Newman Todd Mineral Resource Estimate at Range of Cutoff Grades 

Indicated ResourcesInferred Resources
Au CutoffTonnesTonnesAu Grade (g/t)Au OuncesAu OuncesTonnesTonnesAu Grade (g/t)Au OuncesAu
GradeOunces
(g/t)
0.417,100,0000.83456,00022,460,0000.80578,000
0.68,640,0001.17325,00010,450,0001.16390,000
0.84,750,0001.55237,0005,430,0001.60279,000
12,970,0001.95186,0003,202,0002.10216,000
1.22,040,0002.35154,0002,244,0002.53183,000

Note: Totals in above tables may differ due to rounding.

Note: All designs and costs in this Preliminary Economic Assessment are preliminary in nature and include both Indicated and Inferred Mineral Resources. Inferred Mineral Resources are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as Mineral Reserves.

Description of Proposed Mining Operations

The PEA contemplates open pit mining of the Newman Todd deposit that would be undertaken by a contractor owing to the relatively small size of the mineral resource. Mining would commence with a 21 month pre‐production period involving the following activities:

  • Construction of a dike at the inflow end of Abate Lake and a water diversion channel, prior to

dewatering of the lake

  • Lake bed sediments and overburden removal

Mining of potentially mineralised material intended for direct feed to the processing plant would occur over 36 months following this pre‐production period.

In the PEA mining is planned using conventional truck and shovel operations. The ramp is constrained to the South‐western side of the proposed open pit to maximise pit slope angles for the majority of the mine  life  and  to  access  pockets  of  potentially  mineralised  material  at  deeper  elevations  on  the northeastern side of the pit. The slope angles used in the mine design were adjusted according to this ramp position.

It is expected that a 98% mining recovery and a dilution factor of 5% will be achieved for the open pit operation. Mining recovery accounts for the ore loss events during mucking due to unclear ore/waste contacts or areas where selectivity cannot be reached. The dilution factor is applied to ore blocks due to the undesired waste tonnes added to the ore in the mining process.

Waste rock removed from the operation would be stored on the waste storage facility which is to be sited to the southeast of the open pit. It is expected that waste rock would be categorised as either potentially acid‐generating or non acid‐generating, although no specific test‐work and classification has been undertaken for this level of study. Owing to the known presence of significant carbonate zones constrained to the waste portions within the Newman Todd Structure, these are expected to provide a substantial neutralisation  effect. On  this basis, there is expected to be sufficient non‐acid‐generating waste  rock  available  for  construction  of  the  walls  for  the  tailings  storage  facility  and  for  capping  of potential acid‐generating waste rock within the waste storage facility.

Metallurgical Testing and Ore Processing

Metallurgical test work was undertaken during 2013 on 11 diamond drill hole intersections (totalling 221.9 kg of material) that characterized the various types of mineralization/alteration and waste rock found within the NTS. Gold mineralization within the NTS is predominantly associated with the presence of sulphides and magnetite as well as pervasive silica alteration, and occasionally associated with the presence of minor sulphides and/or magnetite.  Combining results of flotation and cyanidation tests, the overall Au recovery, with regrinding, was approximately 91% for the sulphide/magnetite‐rich composite approximately  92%  for  the  sulphide/magnetite‐poor  composite,  and  approximately  82%  for  an arsenopyrite‐rich composite.  The presence of arsenopyrite and galena, while not particularly abundant, is often a good indicator for the presence of gold.

Processing would involve crushing, gravity separation, flotation and carbon‐in‐pulp leaching to produce gold doré bars. Tailings would be disposed of in a tailings storage facility that is constructed as an initial starter dam and progressively expanded as production from the operation progresses to minimise early capital expenditure. The processing plant would be operated by the owners of the project.

Capital and operating costs

Capital and operating costs are summarised in Tables 4 and 5.

Table 4 Capital Cost Summary

Cost AreaInitial Capital (CA$M)Expansion andTotal Capital (CA$M)
Sustaining
Capital
(CA$M)
R Roads1.51. 1.5
Buildings and Electrical1 1.3
Power line extension and Admin.8.4
Processing Plant & Tailings Management Facility37.0
Infill and Sterilisation Drilling0.6
Contingency (Initial Capital)9.8
Sustaining Capital (Tailings Storage Facility and Process Plant Water Management)23.2
Mine Closure5.1
Contingency (Sustaining Capital)2.1
TOTAL58.630.589.1

A  Table 5 Operating Cost Summary  A 

Cost AreaOperating Cost (CA$/t milled)
Mine39.0
Processing Plant28.7
G&A5.9
Royalties4.7
TOTAL78.3pansion

M) 

and 

Economic and Sensitivity Analysis

The Newman Todd Project is subject to several royalties based either on Net Smelter Return (NSR) or Net Carried Interest (NCI). Those royalties for the project that are based on NSR have been applied to the revenue from payable gold, less the selling costs. However, the royalty based on NCI was not applied in the optimisation phase of the project because, under its terms, it will only result in a payable amount after the recovery of all operating costs, capital expenditures, a carrying charge calculated at prime plus 1% and a reserve for working capital. In this calculation, capital expenditures also include all moneys expended prospecting, exploring and developing the property prior to commercial production.  The NCI‐ based  royalty  has  been  applied  later  in  the  cash  flow  model.    Economic  analysis  on  Newman  Todd Project shows a cash flow after capital depreciation of ‐CA$66.9M and a NPV (5% discount rate) of – CA$62.4M.taining Capital 

(CA$M) 

A  sensitivity  analysis  was  conducted  on  key  economic  inputs:  gold  price  /  feed  grade  /  processing recovery, processing cost, mining cost, capital expenditure and mining recovery.  This analysis indicates that the Project is most sensitive to gold price, processing recovery, feed grade and capital expenditure, followed by mining cost, mining recovery and processing cost.

Ralph  Bullis,  P.Geo,  FGC,  is  the  Qualified  Person  as  defined  by  National  Instrument  43‐101  and  has reviewed or supervised the preparation of the technical content relating to the disclosed document.

On behalf of the Board of Directors,

Confederation Minerals Ltd. 

“Lawrence Dick” 

Lawrence A.Dick, Ph.D., P.Geo  CEO, and Director 

CORPORATE INQUIRIES Confederation Minerals Ltd.

Suite 1980, 1075 West Georgia Street Vancouver, B.C.

Lawrence Dick, CEO 604.688.9588 [email protected] www.confederationmineralsltd.com$M)

About CFM 

Confederation Minerals Ltd. is a British Columbia based company engaged in the business of acquisition, exploration  and  development  of  mineral  properties.  Its  objective  is  to  locate  and  develop  economic precious and base metals properties of merit. Confederation Minerals Ltd. holds an Option Agreement to acquire up to 70% of the Newman Todd project in the Red Lake Mining District of Northern Ontario, as well as 100% ownership in another property in the Red Lake Mining District of Ontario.

Cautionary Note concerning estimates of Measured, Indicated and Inferred Mineral Resource

This news release uses terms that comply with reporting standards in Canada and certain estimates are made in accordance  with  Canadian  National  Instrument  43‐101  ("NI  43‐101"). NI  43‐101  is  a  rule  developed  by  the Canadian Securities Administrators that establishes Canadian standards for all public disclosure an issuer makes of scientific  and  technical  information  concerning  mineral  projects. These  standards  differ  significantly  from  the requirements of the U.S. Securities and Exchange Commission ("SEC"), and mineral resource information contained herein may not be comparable to similar information disclosed by United States companies.

This  news  release  uses  the  terms  "measured  mineral  resources",  "indicated  mineral  resources"  and  "inferred mineral resources" to comply with reporting standards in Canada. We advise United States investors that while such terms are recognized and required by Canadian regulations, the SEC does not recognize them. United States investors are cautioned not to assume that any part or all of the mineral deposits in such categories will ever be converted into mineral reserves under SEC definitions. These terms have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. Therefore, United States investors are also  cautioned  not  to  assume  that  all  or  any  part  of  the  "measured  mineral  resources",  "indicated  mineral resources" or "inferred mineral resources" exist. In accordance with Canadian rules, estimates of "inferred mineral resources" cannot form the basis of pre‐feasibility or other economic studies. It cannot be assumed that all or any part of the "measured mineral resources", "indicated mineral resources" or "inferred mineral resources" will ever be upgraded to a higher category.

Forward‐Looking Information  

This release includes certain statements that may be deemed "forward‐looking statements". All statements in this release, other than statements of historical facts, that address events or developments that the Company expects to occur, are forward‐looking statements. Forward‐looking statements are statements that are not historical facts and are generally, but not always, identified by the words "expects", "plans", "anticipates", "believes", "intends", "estimates", "projects", "potential" and similar expressions, or that events or conditions "will", "would", "may", "could" or "should" occur. Although the Company believes the expectations expressed in such forward‐looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results may differ materially from those in the forward‐looking statements. Factors that could cause the actual results to differ materially from those in forward‐looking statements include market prices, exploitation and exploration  successes,  and  continued  availability  of  capital  and  financing,  and  general  economic,  market  or business conditions. Investors are cautioned that any such statements are not guarantees of future performance and actual results or developments may differ materially from those projected in the forward‐looking statements. Forward‐looking statements are based on the beliefs, estimates and opinions of the Company's management on the date the statements are made. Except as required by applicable securities laws, the Company undertakes no obligation  to  update  these  forward‐looking  statements  in  the  event  that  management's  beliefs,  estimates  or opinions, or other factors, should change.