Saturday, October 17, 2026
MiningNewsTerminal
Saturday, October 17, 2026 Admin

K.TO ·

Kinross provides update on organic development projects and full-year 2017 exploration results Five projects advancing on schedule and on budget; three development opportunities proceeding well Tasiast two-phased expansion on track, with Phase One production expected by end of June

Exploration Programs

TORONTO, Feb. 14, 2018 -- Kinross Gold Corporation (TSX:K) (NYSE:KGC) provided today updates to its organic development projects, exploration program and its estimated mineral reserves and resources.

(This news release contains forward-looking information about expected financial and operating performance of the Company. All mineral reserves and mineral resources, as well as mine life disclosures, are estimates.)

Organic development projects:

  • Tasiast Phase One: Proceeding on schedule and on budget and is expected to commence full commercial production by the end of June. Plant construction is now 93% complete.
  • Tasiast Phase Two: On schedule to commence construction as Phase One nears completion. Phase Two is expected to begin commercial production in Q3 2020 and transform Tasiast into a large, world-class operation, with low costs and a long mine life.
  • Round Mountain Phase W: Stripping and initial construction commenced ahead of schedule in late 2017, with all major permits now received. Initial low grade Phase W ore is expected to be encountered in mid-2019.
  • Bald Mountain Vantage Complex: Proceeding on schedule with commissioning for the proposed heap leach pad and processing facilities expected to commence in Q1 2019.
  • Moroshka: Proceeding on schedule and on budget with mining of high-grade ore expected to begin in the second half of the year for processing in the Kupol mill.
  • Fort Knox Gilmore: Company expects to complete a feasibility study in mid-2018. Kinross added 2.1 million Au oz. in estimated measured and indicated resources and 300 koz in estimated inferred resources1 after gaining mineral rights to Gilmore land.
  • Tasiast Sud: Pre-feasibility study on schedule to be completed in the second half of 2018. Kinross added 820 Au koz. to estimated inferred resources after completing a 2017 drilling program at the project.
  • La Coipa Restart: Company has agreed to acquire the 50% of the Phase 7 deposit it did not already own to gain full ownership and related mining rights. In 2017, the Company added 844 koz. of gold and 34 million oz. of silver to mineral reserve estimates from the Phase 7 and Puren deposits, which comprise the La Coipa Restart project.

Exploration and Mineral Reserves and Resources update1:

  • The Company added approximately 4.0 million oz. to its proven and probable mineral reserve estimates in 2017 to offset depletion of 3.2 million Au oz., mainly due to additions of approximately 2.3 million Au oz. at Round Mountain, 844 koz. at La Coipa, 273 koz. in Russia, 332 koz. at Paracatu and 254 koz. at Fort Knox.
  • Additions to estimated mineral reserves are expected to extend mining at Round Mountain by five years, Fort Knox mine life by one year, mill production at Kupol by one year and Paracatu mine life to 2032.
  • Mineral reserve estimates at year-end 2017 were 25.9 million Au oz. compared with 31.0 million Au oz. at year-end 2016, as the sale of Cerro Casale and depletion was partially offset by mineral reserve additions.
  • Measured and indicated mineral resource estimates were 29.6 million Au oz., and are largely in line with 30.3 million Au oz. at year-end 2016. Net additions of 1.8 million oz. at Fort Knox and 461 koz. at Round Mountain largely offset the net decrease, which was mainly as a result of the sale of Cerro Casale and White Gold.
  • In 2018, Kinross is prioritizing exploration drilling at several operations, including Kupol, Tasiast Sud, and Bald Mountain, as the Company continues to focus on promising brownfield opportunities for mineral resource and reserve additions.

CEO commentary

J. Paul Rollinson, President and CEO, made the following comments in relation to Kinross’ organic development projects:

“Our five development projects and three development opportunities all made great progress in 2017 and are proceeding on schedule and on budget. We achieved key project milestones during the year and are in a strong position to continue executing according to our plan. These projects are expected to increase production or extend life of mine in our portfolio and are the foundation of our future growth.

“The two-phased Tasiast expansion is on schedule and on budget, with full commercial production at Phase One expected by the end of June, and Phase Two development preparations well on their way to ensure continuity with the project management teams. Our Nevada projects are proceeding as planned, with Round Mountain Phase W now in construction and the Bald Mountain Vantage Complex scheduled for commissioning in Q1 2019. In 2018, we also expect to begin mining high-grade ore at Moroshka, complete the Fort Knox Gilmore project feasibility study, complete the Tasiast Sud pre-feasibility study, and receive the remaining sectoral permits for the La Coipa Restart project.

“Our exploration program delivered meaningful ounces to our operations, as we added more than 3.5 million ounces to measured and indicated mineral resource estimates. We also added approximately four million ounces to mineral reserve estimates to offset depletion, and expect to extend mine life at key operations across our portfolio.”

Organic development projects

Tasiast Phase One and Phase Two expansion

Tasiast Phase One project development is progressing well, and continues to be on time and on budget, with full commercial production expected by the end of June. Plant construction is now 93% complete and the remaining work is now focused on electrical, instrumentation and controls installations. Mechanical installation of the primary crusher, conveyor, stockpile and CIL (carbon-in-leach) plant modifications, which includes the cyclones, three leach tanks and elution circuit, are now substantially complete. Commissioning of the primary crusher and CIL plant is expected to begin in late February, and the SAG mill in April.

The Tasiast Phase Two project is proceeding on schedule, as Phase One nears completion. Project and construction teams are expected to transition from Phase One to Phase Two development to establish continuity between projects. Overall engineering is now 33% complete and procurement is progressing well, with the power plant and EPCM contracts now awarded. Early works for the ball mill and power plant are expected to commence in Q2 2018. Phase Two is expected to begin commercial production in Q3 2020 and transform Tasiast into a large, world-class operation, with low costs and a long mine life.

Round Mountain Phase W

At the Round Mountain Phase W project, stripping, initial construction and site preparation activities commenced ahead of schedule in late 2017 after the receipt of the Decision Record and other approvals from the U.S. Bureau of Land Management. The construction management team has been mobilized to site and earthworks have begun in the project area. Detailed engineering is progressing on schedule, with heap leach engineering complete and mine infrastructure and processing facility engineering approximately 50% complete. Procurement activities are underway for critical long lead items and tracking according to plan. State permitting is proceeding as planned, with all major permits now received. The project remains on schedule, with initial low grade Phase W ore expected to be encountered in mid-2019.

Bald Mountain Vantage Complex

The Bald Mountain Vantage Complex project is proceeding on schedule, with initial construction work now well underway and engineering more than 80% complete. Permitting is proceeding as planned and contractors for more than half the scope of the project work have been selected. Commissioning for the proposed heap leach pad and processing facilities is expected to commence in Q1 2019.

Moroshka project

At the Moroshka satellite deposit in Russia, located approximately four kilometres east of Kupol, development of the twin declines continues to proceed on schedule and on budget. Mining of high-grade ore at Moroshka is expected to commence in the second half of 2018 for processing in the Kupol mill.

Fort Knox Gilmore

At the Fort Knox Gilmore project, permitting activities have commenced and feasibility study activities are ongoing. The feasibility study, which is expected to be completed in mid-2018, is assessing a multi-phase layback of the Fort Knox pit and the construction of a new heap leach pad. Kinross gained mineral rights to the Gilmore land, which is located immediately west of the Fort Knox pit, on December 12, 2017. As a result, the Company added 2.1 million gold ounces in estimated measured and indicated resources and 300 koz. in estimated inferred resources. This was offset by a conversion of 254 koz. of mineral resources to mineral reserves, for a net addition of 1.8 million ounces to measured and indicated resource estimates. An additional 199 koz. was added to estimated inferred resources from exploration and engineering for a total increase of 499 koz. to inferred resource estimates.

Fort Knox Mineral Reserve and Mineral Resource Estimates1
2016 (Au koz)Depletion (Au koz)Gilmore Addition (Au koz)Other Exploration / Engineering Changes (Au koz)2017* (Au koz)
Proven and Probable Reserves1,506(515)-2541,245

Measured and Indicated Resources 1,440 0 2,100 (311) 3,229 Inferred Resources 193 (3) 300 199 689

*Totals may not fully add up due to rounding.

Tasiast Sud project

The Tasiast Sud pre-feasibility study (PFS) is proceeding as planned and is expected to be completed in the second half of 2018. The PFS is contemplating a potential dump leach operation that would combine materials from multiple deposits in the area, and the trucking of high grade ore to the Tasiast mill, located approximately 10 kilometres north of the project. The Company added approximately 820 koz. to inferred mineral resource estimates at Tasiast Sud in 2017.

La Coipa Restart project

On February 2, 2018, the Company agreed to acquire 50% of the Phase 7 deposit from its joint venture partner to consolidate ownership. Upon completion of the transaction, the Company will have mining rights contemplated by the project pre-feasibility study (PFS) completed in 2015 and will fully own the Phase 7 deposit. The transaction includes payments totalling $65 million ($35 million on closing and $30 million on or before January 31, 2019) and is subject to certain conditions. The transaction is expected to close within 90 days.

In 2017, approximately 844 koz. of gold and 34 million oz. of silver at Phase 7 and Puren, which comprise the La Coipa Restart project, was converted to estimated mineral reserves from estimated mineral resources. The scope of work contemplated by the project PFS included modifications and enhancements to the existing plant and infrastructure in order to allow blending and processing of higher grade material from the Phase 7 deposit with oxide/transition material from the existing Puren deposit. The Company received approval on the project DIA (Declaration of Impact to Environment) permit in 2016 and expects to receive sectoral permits in the first half of 2018.

Paracatu optimization study update

Kinross has recently completed initial optimization and analysis work for Paracatu that has reaffirmed the Company’s view of the operation’s value and its position as a long-life, large producing mine in Kinross’ portfolio.

The optimization and analysis work focused on determining the optimal mine plan after taking into account improvements undertaken at Paracatu over the past few years. These improvements include the successful reprocessing of tailings, the blending of ores to extend Plant 1 life, and several other continuous improvement initiatives. The optimization work also assessed the impact of throughput variances in quartzite‐impacted zones, lower realized recoveries in certain zones of the ore body, water mitigation projects, local cost inflation, and changes to the fiscal regime in Brazil.

The initial technical work, which included geochemical and metallurgical studies, has advanced the Company’s understanding of the operation’s large and varied orebody. The optimization analysis, combined with the implementation of an improved ore control program, is expected to increase the consistency and predictability of Paracatu’s throughput and recovery over the life of mine, partly due to the improved ability to identify ore zones for ideal blending. The technical work resulted in an increase of 332 koz. to the site’s mineral reserve estimates before 2017 depletion, and expects to extend Paracatu’s mine life to 2032.

The Company also announced today that its wholly-owned subsidiary, Kinross Brasil Mineraçao, has agreed to acquire two hydroelectric power plants in Brazil from a subsidiary of Gerdau SA for $257 million2. The two plants are expected to provide 70% of Paracatu’s power and reduce production cost of sales per ounce by approximately $80 over life of mine3. The Company expects to further analyze the benefits of the acquisition of the two hydroelectric power plants on the optimal mine plan and complete the optimization work, which will also include further ore characterization and throughput improvement projects, by the end of 2018.

2017 Mineral Reserves and Mineral Resources update

(See also the Company’s detailed Annual Mineral Reserve and Mineral Resource Statement estimated as at December 31, 2017 and explanatory notes starting at page 14.)

In preparing the Company’s 2017 year-end mineral reserves and mineral resource estimates as of December 31, 2017, Kinross has maintained gold price assumptions used since 2011 of $1,200 per ounce for mineral reserves and $1,400 per ounce for mineral resources. Kinross continued to focus on estimated higher margin, lower cost ounces, and maintained its fully-loaded costing methodology.

Proven and Probable Mineral Reserves1

Kinross’ total proven and probable gold reserve estimate was 25.9 million ounces at year-end 2017 compared with 31.0 million ounces at year-end 2016. The net year-over-year decrease was mainly the result of the sale of Cerro Casale, which accounted for 5.8 million ounces in estimated mineral reserves. The Company added approximately 4.0 million Au oz. to its mineral reserve estimates in 2017 to offset depletion of 3.2 million Au oz. during the year. The additions, before depletion, to estimated mineral reserves include:

  • 2.3 million oz. at Round Mountain
  • 844 koz .at La Coipa
  • 332 koz. at Paracatu
  • 273 koz.at Kupol-Dvoinoye
  • 254 koz. at Fort Knox (East Wall)

As a result of these mineral reserve additions and engineering and mine optimization work, the Company expects to extend mining at Round Mountain by five years, mine life at Fort Knox by one year, mill production at Kupol by one year and Paracatu mine life to 2032.

Proven and probable silver reserves at year-end 2017 were estimated at approximately 52.6 million ounces, compared with 37.4 million ounces at year-end 2016. The increase was mainly as a result of additions of approximately 34.0 million oz. of silver at La Coipa, partially offset by the sale of Cerro Casale, which accounted for 14.7 million silver oz., and production depletion. Silver reserves were estimated using a silver price assumption of $17.00 per ounce.

The Company no longer has any proven and probable copper reserves, which were exclusively at Cerro Casale.

Measured and Indicated Mineral Resources1

Kinross’ total estimated measured and indicated mineral resources at year-end 2017 were 29.6 million Au oz. and in line with mineral resource estimates of 30.3 million Au oz. at year-end 2016. Mineral resource additions of approximately 1.8 million oz. at Fort Knox, 489 koz. at Round Mountain and 119 koz. at Kupol partially offset the decrease in mineral resource estimates as a result of the sale of Cerro Casale and White Gold and the conversion of gold ounces to mineral reserves.

Measured and indicated silver resources were estimated to be 35.5 million ounces, assuming a $20.00 per ounce silver price, compared with 70.9 million ounces at year-end 2016. The decrease was mainly as a result of the conversion of silver ounces at La Coipa to estimated mineral reserves.

Inferred Mineral Resources1

Kinross’ total estimated inferred gold resources at year-end 2017 were approximately 6.4 million ounces, compared with 6.5 million ounces at year-end 2016. The slight net decrease was primarily a result of the sale of Cerro Casale and conversions of ounces to mineral reserves and measured and indicated resources. The decrease was largely offset by inferred mineral resource additions, including:

  • 898 koz. at Tasiast, which includes approximately 820 koz. at Tasiast Sud
  • 499 koz. at Fort Knox
  • 282 koz. at the Round Mountain Phase W project
Kinross Gold Mineral Reserve and Mineral Resource Estimates1
2016 (Au koz)Divestiture (Au koz)Depletion (Au koz)Exploration (Au koz)Engineering (Au koz)2017* (Au koz)
Proven and Probable Reserves30,965(5,811)(3,212)3683,62825,934
Measured and Indicated Resources30,280(1,683)(103)3,570(2,469)29,594
Inferred Resources6,473(1,623)(51)(180)1,7616,382

*Totals may not fully add up due to rounding.

Exploration update

The Company’s exploration efforts continued to focus within the footprint of existing mines and their immediate surrounding districts in 2017. A total of 368 koz was added to Kinross’ estimated mineral reserves and 3.57 million ounces was added to measured and indicated mineral resource estimates due to exploration activities during the year. 2017 exploration highlights include:

  • Kupol-Dvoinoye: A total of 273 Au koz. was added to estimated mineral reserves and 113 Au koz. to estimated measured and indicated resources, mainly from Kupol and Zone 1 and Zone 37 at Dvoinoye. At Kupol, the primary objective of 2017 drilling in the North Extension area was to determine the extent of mineralization. Drill intercepts continue to confirm high-grade narrow-vein mineralization extending northwards by up to two kilometres from the current limit of the Kupol mine workings. As a result of continued exploration success at Kupol and engineering optimization work at Dvoinoye, scheduled mill production at Kupol has been extended by one year to 2022.
  • Tasiast Sud: Drilling at Tasiast Sud mainly targeted the C6.13 and C6.15 deposits, which are located immediately south of the Tasiast mine and west of the Tamaya deposit. Resource model updates for the two deposits added approximately 670 Au koz. to inferred mineral resource estimates.

For 2018, the brownfields exploration program will follow up on the mineralized targets identified in 2017 with infill drilling and geologic modelling, with the goal of converting the mineralization to estimated measured, indicated and inferred mineral resources.

  • Kupol: Kinross is expected to increase exploration spending to $14.5 million in 2018 to continue exploring and delineating high potential targets in the Kupol land package, particularly the North Extension, where high-grade narrowvein targets have been identified. A tighter spacing drill program is expected to be undertaken to determine the potential for additions to inferred resource estimates.
  • Tasiast Sud: A pre-feasibility study is expected to be completed in the second half of 2018. Exploration programs are expected to focus on testing the extent of mineralization at depth in C6.13 and C6.15, as well as C6.14 and C6.16, which are within the Tasiast Sud area. Exploration at Tasiast is expected to be focused on both the potential for nearsurface leachable oxide targets and deeper granodiorite-hosted targets.
  • Bald Mountain: Kinross expects to spend [$10 million] at Bald Mountain in 2018 for infill drill programs with the goal of upgrading estimated mineral resources to mineral reserves at Redbird, Winrock and Yankee. Exploration will also focus on other target areas for mineral resource growth, including the Redbird extension, Winrock extensions and Top Gap.
  • Kettle River - Curlew: Kinross plans to dewater and rehabilitate the historic K2 mine in order to conduct underground exploration drilling to better target the extensions of mineralization identified at multiple targets in 2017.
  • Chirano: Mineralization at depth is a key exploration focus for 2018, particularly at Akwaaba and Paboase. The Company will assess its mineral reserve estimates at the conclusion of the 2018 exploration program.

A more detailed summary of the 2017 highlights is presented below. Additional details may be found in the Appendices. “Appendix A” provides illustrations, captions, and accompanying explanatory notes, and “Appendix B” provides complete drilling results and drill hole location data corresponding to the values below.

Appendix A: http://www.kinross.com/files/doc_news/2018/02/Appendix-A_Q4-YE-2017-ExplorationFigures_February- 14.pdf Appendix B: http://www.kinross.com/files/doc_news/2018/02/Appendix-B_Q4-YE-2017-Exploration-Drill- Results_February-14.xlsx

Kupol - Dvoinoye

As a result of continued exploration success at Kupol and engineering optimization work at Dvoinoye, scheduled mill production at Kupol has been extended by one year to 2022. As has been the case in previous years, the results of the exploration program have successfully yielded additions to mineral reserve and resource estimates, including a total of approximately 273 Au koz added to the Russia region’s estimated mineral reserves before depletion, mainly from Kupol’s Southeast Extension and in Zone 1 and Zone 37 at Dvoinoye. At the Kupol Northeast Extension, a total of approximately 113 Au koz. was added to the site’s measured and indicated mineral resource estimates.

A total of 79,128 metres were drilled at Kupol during 2017, mainly at the North and South Extensions of the main Kupol vein (see Appendix A: Figure 1). In Zone 650 Southeast Extension (See Appendix A: Figure 2) approximately 90 Au koz. was added to Kupol’s estimated mineral reserves. Drill results in the Northeast and Northern Extension have demonstrated that mineralization is similar to those previously documented at Big Bend and the Central Zone, although at narrower widths. Drilling at the Northern Extension also identified a hanging wall mineralization approximately 150 metres east of the main Kupol vein. These include extensional and fault-hosted veins with well-developed cataclastic breccias, which core axis angles suggest dip steeply to the west. In the Northern extension, exploration work in 2018 is expected to focus on tighter-spaced drilling with the intent of identifying an inferred mineral resource.

A total of 26,045 metres were drilled at Dvoinoye, with emphasis at Zone 1 and Zone 37, both proximal to site operations. Infill drilling resulted in the conversion of 186 koz. Au to estimated mineral reserves in these two zones, while additional mineralization was intersected north of Zone 1 along strike. Follow-up drilling in 2018 is expected to focus on the northern extension of Zone 1 and Zone 37, as well as regional targets around the mining license.

Kinross is expected to increase exploration spending in Russia to approximately $18.5 million in 2018 to continue exploring high potential targets in the Kupol and Dvoinoye land packages. For full drill results and explanatory notes see Appendix B.

Kupol Mining Licence and Kupol West Property significant down-hole drill intercepts:

Hole IDFromToInterval (m)True Width (m)Au (g/t)Ag (g/t)
Northeast Extension
KP17-1324409.4413.33.93.570.37740.16
KP17-1326397.7399.82.11.8121.111197.63
KP17-1335324.8328.73.93.242.38163.14
Including327.6328.20.60.6244.0758.0
Hanging Wall
KP17-1292230.5233.22.71.52.0720.72
KP17-1290379.5380.20.70.412.6812.68
Kupol Mineral Reserve and Mineral Resource Estimates1
2016 (Au koz)Depletion (Au koz)Exploration & Engineering (Au koz)2017* (Au koz)
Proven and Probable Reserves1,683(335)871,435
Measured and Indicated Resources1990119317
Inferred Resources131016146

*Totals may not fully add up due to rounding.

Dvoinoye Mineral Reserve and Mineral Resource Estimates1
2016 (Au koz)Depletion (Au koz)Exploration & Engineering (Au koz)2017* (Au koz)
Proven and Probable Reserves619(228)186576
Measured and Indicated Resources420(36)6
Inferred Resources1080(103)5

*Totals may not fully add up due to rounding.

Tasiast Sud

In 2017, all exploration drilling at Tasiast was conducted at Tasiast Sud, where 541 drill holes for 47,468 metres were completed. The main target areas were the C6.13 and C6.15 deposits (see Appendix A: Figure 3), which are located immediately south of the Tasiast mine and west of the Tamaya deposit.

Drilling to date has identified continuous mineralization along an 8 kilometre strike between C6.13 to C6.15, up to a depth of 200 metres, with an oxide transition boundary approximately 100 metres from surface. Resource model updates for the two deposits have generated approximately 670 Au koz. for Tasiast’s inferred mineral resource estimates.

A refined model at Tamaya has also added approximately 150 Au koz to inferred mineral resource estimates, bringing total inferred mineral resource estimates at Tasiast Sud to approximately 820 Au koz.

There is an application pending to convert an exploration license to an exploitation license, which is required in order to maintain the Company’s rights to the Tasiast Sud land.

Exploration programs testing the extension of mineralization at depth in C6.13 and C6.15, as well as C6.14 and C6.16, which are within the Tasiast Sud area, are expected to continue in 2018. For full drill results and explanatory notes see Appendix B.

Tasiast Sud significant down-hole drill intercepts:

Hole IDFromToInterval (m)Au (g/t)
C6.13
TA13727RC1836184.08
TA13732RC1021117.15
TA14747RC32491711.42
C6.15
TA14780RC515984.51
TA16607RC6678122.96
TA16614RC4568232.71
Tasiast Mineral Reserve and Mineral Resource Estimates1
2016 (Au koz)Depletion (Au koz)Exploration & Engineering (Au koz)2017* (Au koz)

Proven and Probable Reserves 8,015 (106) (49) 7,861

Measured and Indicated Resources3,144(39)(146)2,959
Inferred Resources345(7)8981,237

*Totals may not fully add up due to rounding.

Round Mountain

At Round Mountain, the exploration program focused on Phase W and completed 10,230 metres of infill drilling, concluding the Phase W exploration program. Approximately 2.3 million Au oz. were converted to mineral reserve estimates. Measured and indicated mineral resource estimates increased by 489 koz. and inferred mineral resources by 282 koz. Exploration drilling in 2018 is expected to target potential ounces in pit wall laybacks to the north and south of the pit, with the aim of upgrading and adding to the site’s mineral resource estimates.

Round Mountain Mineral Reserve and Mineral Resource Estimates1
2016 (Au koz)Depletion (Au koz)Exploration & Engineering (Au koz)2017* (Au koz)
Proven and Probable Reserves1,267(648)2,2662,884
Measured and Indicated Resources1,932(28)4892,393
Inferred Resources1,863(30)2822,115

*Totals may not fully add up due to rounding.

Bald Mountain

During 2017, exploration at Bald Mountain focused on near term opportunities that are expected to have a direct impact on operational planning, as well as growing existing mineral resource estimates and defining future opportunities within the large Bald Mountain land package (see Appendix A: Figure 4).

Approximately $10 million was spent on the 2017 Bald Mountain exploration program, which completed 52,295 metres of drilling in 319 holes. Drilling was completed at the Redbird, Winrock, Top, Saga, Poker Flat, Duke, Rat and White Pine deposits in the North Area, and at the Luxe and Yankee deposits in the South Area. Additional drill testing was completed on early stage targets within the Joint Venture and the North Area.

In the North Area, exploration drilling at Redbird focused on testing the south extent of mineralization and infill drilling (see Appendix A: Figure 5). The extension drilling expanded the mineralization potential of the current estimated mineral resource, with significant high grade upside up to 300 metres southeast of the current pit design. The Winrock drill program returned positive intercepts, which has led to an addition of mineral resource ounces in the shallow oxide zones (see Appendix A: Figure 6). The drill program completed at Saga extended mineralization and also confirmed gaps in mineralization within the design pits and moderate step outs with significant grades to the east and at depth of the current mineral resource. Infill drilling at the south wall of the Top 2 pit (Top Gap) indicated continuity of mineralization along the Skarn Fault. Exploration drilling at Top Hat, in the northwest area of the Top 2 pit, intersected mineralization outside of the current resource model. For full drill results and explanatory notes see Appendix B.

Bald Mountain significant down-hole drill intercepts:

Hole IDFromToInterval (m)Au (g/t)
Redbird
RB17-001213.4259.145.74.15
RB17-015102.1167.665.52.74
RB17-016166.1243.877.72.54
Winrock
WR17-0371.5112.8111.30.77
WR17-0483.045.742.71.37
WR17-0520.032.032.02.25
Top
TE17-040318.5332.213.79.91
TE17-057105.2134.129.03.20
TE17-06648.8137.288.47.06
Including48.856.47.634.78
Also including111.3137.225.910.16

Saga

SG17-010192.0295.7103.60.75
SG17-017109.7153.944.21.92
SG17-03873.0185.9112.80.76

Drilling within the Bald Mountain Joint Venture Area has confirmed a large footprint of a mineralized system within the Guilmette Limestone at Rattlesnake.

In 2018, Kinross expects to spend $10 million at Bald Mountain for infill drill programs with the goal of upgrading estimated mineral resources to mineral reserves at Redbird, Winrock and Yankee and adding to the mineral resource estimates in the Top 2 pit. In addition, 2018 exploration is expected to focus on early stage upside targets within the large Bald Mountain land package, and other target areas for mineral resource growth, including the Redbird extension, Winrock extensions and Top Gap.

Bald Mountain Mineral Reserve and Mineral Resource Estimates1
2016 (Au koz)Depletion (Au koz)Exploration & Engineering (Au koz)2017* (Au koz)
Proven and Probable Reserves2,133(525)911,698
Measured and Indicated Resources3,5480(200)3,349
Inferred Resources6480(51)597

*Totals may not fully add up due to rounding.

Fort Knox

In December 2017, Kinross announced that it had gained mineral rights to the Gilmore property, which is located immediately west of the Fort Knox pit. Kinross began an initial drilling program on Gilmore land, and Fort Knox land adjacent to Gilmore, in 2014, completing approximately 73,000 metres of core and reverse-circulation drilling in 205 holes (see Appendix A: Figure 7).

In addition to Gilmore, Kinross continued to explore the extent of mineralization to the east of the Fort Knox pit. During the year, 2,717 metres were drilled in the East Wall of the pit. For full drill results and explanatory notes see Appendix B.

Gilmore Property significant down-hole drill intercepts:

Hole IDFromToInterval (m)Au (g/t)
FFR16-1585294.10304.8010.704.12
FFC17-159574.7094.5019.801.28
FFC17-1690362.70373.4010.705.23

Kettle River - Curlew

The early stage Curlew district exploration program continued to focus in and around the historical K2 mine, which is 37 km away from the Kettle River mill. A total of 11,929 metres of drilling was completed to define gaps in discreet mineralized zones at K2 North, Z3, Emanuel Creek, Stealth, Lower East Vein, K5 and Lower Portal, and to extend mineralization along strike. Significant intercepts were also intersected in quartz adularia veins north and east of the current K5 and Lower Portal zones (see Appendix A: Figure 8).

Kinross expects to continue to explore these zones in 2018, and plans to dewater and rehabilitate the K2 mine in order to conduct underground exploration drilling to better target the extensions of mineralization identified in 2017. For full drill results and explanatory notes see Appendix B.

Curlew significant down-hole drill intercepts:

Hole IDFromToInterval (m)True Width (m)Au (g/t)
Lower Portal
LP17-21394.5418.824.324.03.71
Including400.8403.72.90.611.43
LP17-24277.4284.77.37.33.84
LP17-25A326.1386.860.715.72.24
K5 Zone
K5-17-17B654.4663.59.17.47.51

K5-17-20 442.1 447.8 5.7 4.5 12.05

Including442.1442.50.40.255.5
K5-17-22A513.7521.88.16.06.45

Chirano

At Chirano, the exploration strategy remains focused on incremental additions to the mine life, which is currently expected to end in 2020. In 2017, the priorities were assessing the potential for depth extensions of the Akwaaba and Paboase underground mines and determining open pit potential in the gap between the Mamnao Central and South pits.

At Akwaaba, drilling has proven the continuity of mineralization in an area that was previously considered a low grade gap (see Appendix A: Figure 9). The 2017 infill drill program has identified a high-grade portion of a hanging wall splay. Generally, drilling has demonstrated potentially mineable material greater than 100 metres below current reserves with the addition of material from the hanging wall splay. Drilling at Paboase also identified continuous mineralization over 100 metres below the current reserves, with significant high grades over appreciable mining widths (see Appendix A: Figure 10). The 2018 drill program will continue to prioritize the depth extensions at both Akwaaba and Paboase.

An active drill program is ongoing and is expected to be completed during 2018. The results of the drill program will be reflected in a mineral resource update in 2018. Any potential impact to mine life at Chirano will be assessed in late 2018 in conjunction with the results of an ongoing cost-cutting and productivity improvement program. For full drill results and explanatory notes see Appendix B.

Chirano Underground significant drill intercepts:

Hole IDFromToInterval (m)True Width (m)Au (g/t)
Akwaaba UG
CHDD2502UG204.2236.031.816.55.25
CHDD2506UG225.8256.230.414.35.03
CHDD2534UG287.0306.019.012.85.71
Paboase UG
CHDD2545UG261.0279.018.09.54.75
CHDD2547UG215.0227.912.98.68.10
CHDD2556UG230.0247.017.09.56.62
Mamnao Gap
CHRC2503262.0280.018.013.03.18
CHRC2530198.0245.047.025.01.46
Including205.0235.030.015.92.02
Including227.0234.07.03.73.49
CHRC2543208.0230.022.015.52.45

Greenfields exploration update

While brownfields exploration remains Kinross’ core exploration focus, the Company also continues to pursue greenfield opportunities. In 2017, Kinross focused on targets in Nevada, the Abitibi region in Quebec and Ontario, areas of Eastern Russia, and northern Finland’s greenstone belts.

Kinross also pursues greenfields opportunities and high margin types of deposits through strategic investments and partnerships with high quality junior exploration companies. The Company believes fostering good relationships with management teams that have a successful track record of discovery, and keeping a solid pipeline of quality targets that demonstrate scope and scale for significant discovery, are key components of the greenfields exploration strategy.

In Nevada, Kinross explored 10 projects in both joint venture (JV) and 100%-owned Kinross claims. Kinross and its JV partners undertook geochemical sampling, ground and airborne geophysical surveys and drilling programs. Indications of mineralization and prospective targets were generated at several projects, and a second phase of drilling is expected to be undertaken in 2018. The Company and its JV partners have also identified new opportunities in Alaska, Quebec, Ontario, the Yukon, and Finland, and are assessing potential drilling programs at these projects for 2018.

Conference call details

In connection with this release and the Company’s 2017 Q4/year-end results, Kinross will hold a conference call and audio webcast on Thursday, February 15, 2018 at 9 a.m. ET to present the results, followed by a question-and-answer session. To access the call, please dial:

Canada & US toll-free – (866) 393-4306; Conference ID: 9094608 Outside of Canada & US – +1 (734) 385-2616; Conference ID: 9094608

Replay (available up to 14 days after the call):

Canada & US toll-free – (855) 859-2056; Conference ID: 9094608 Outside of Canada & US – +1 (404) 537-3406; Conference ID: 9094608

You may also access the conference call on a listen-only basis via webcast at our website www.kinross.com. The audio webcast will be archived on our website at www.kinross.com.

This release should be read in conjunction with Kinross’ 2017 Q4/year-end news release, 2017 year-end Financial Statements and Management’s Discussion and Analysis report at www.kinross.com. Kinross’ 2017 year-end Financial Statements and Management’s Discussion and Analysis have been filed with Canadian securities regulators (available at www.sedar.com) and furnished with the U.S. Securities and Exchange Commission (available at www.sec.gov). Kinross shareholders may obtain a copy of the financial statements free of charge upon request to the Company.

About Kinross Gold Corporation

Kinross is a Canadian-based senior gold mining company with mines and projects in the United States, Brazil, Russia, Mauritania, Chile and Ghana. Our focus is on delivering value based on the core principles of operational excellence, balance sheet strength, disciplined growth and responsible mining. Kinross maintains listings on the Toronto Stock Exchange (symbol:K) and the New York Stock Exchange (symbol:KGC).

Media Contact

Louie Diaz Director, Corporate Communications phone: 416-369-6469 [email protected]

Investor Relations Contact

Tom Elliott Senior Vice-President, Investor Relations and Corporate Development phone: 416-365-3390 [email protected]

2017 Annual Mineral Reserve and Resource Statement

Proven and Probable Mineral Reserves

MINERAL RESERVE AND MINERAL RESOURCE STATEMENT GOLD PROVEN AND PROBABLE MINERAL RESERVES (1,3,4,5,6,8) Kinross Gold Corporation's Share at December 31, 2017
PropertyLocationKinross InterestProvenProbableProven and Probable
TonnesGradeOuncesTonnesGradeOuncesTonnesGradeOunces
(%)(kt)(g/t)(koz)(kt)(g/t)(koz)(kt)(g/t)(koz)
NORTH AMERICA
Bald MountainUSA100.0%6,4900.714388,7260.51,55595,2160.61,698
Fort Knox AreaUSA100.0%23,6710.535765,1870.488888,8580.41,245
Round Mountain AreaUSA100.0%49,2660.585375,1160.82,031124,3820.72,884
SUBTOTAL79,427 0.5 1,353229,029 0.6 4,474308,456 0.6 5,827
SOUTH AMERICA
La Coipa 8Chile100.0%591.6315,6031.784115,6621.7844
ParacatuBrazil100.0%511,1270.46,805131,1940.52,019642,3210.48,824

SUBTOTAL 511,186 0.4 6,808 146,797 0.6 2,860 657,983 0.5 9,668

AFRICA
ChiranoGhana90.0%3,6391.01224,6623.04458,3012.1567
TasiastMauritania100.0%30,5351.21,19194,2542.26,670124,7892.07,861
SUBTOTAL34,174 1.2 1,31398,916 2.2 7,115133,090 2.0 8,428
RUSSIA
DvoinoyeRussia100.0%1,2875.22161,2968.63602,5836.9576
KupolRussia100.0%7706.21554,8088.31,2805,5788.01,435
SUBTOTAL2,057 5.6 3716,104 8.4 1,6408,1617.72,011
TOTAL GOLD626,844 0.5 9,845480,846 1.0 16,0891,107,690 0.7 25,934
MINERAL RESERVE AND MINERAL RESOURCE STATEMENT SILVER PROVEN AND PROBABLE MINERAL RESERVES (1,3,4,5,6,8) Kinross Gold Corporation's Share at December 31, 2017
PropertyLocationKinross InterestProvenProbableProven and Probable
TonnesGradeOuncesTonnesGradeOuncesTonnesGradeOunces
(%)(kt)(g/t)(koz)(kt)(g/t)(koz)(kt)(g/t)(koz)
NORTH AMERICA
Round Mountain AreaUSA100.0%3,6526.17133,6415.66587,2935.81,371
SUBTOTAL3,652 6.1 7133,641 5.6 6587,293 5.8 1,371
SOUTH AMERICA
La Coipa 8Chile100.0%59152.929115,60367.633,89715,66267.934,188
SUBTOTAL59 152.9 29115,603 67.6 33,89715,662 67.9 34,188
RUSSIA
DvoinoyeRussia100.0%1,2879.74021,29613.15442,58311.4946
KupolRussia100.0%77081.82,0254,80891.114,0865,57889.816,111
SUBTOTAL2,057 36.7 2,4276,10474.614,6308,161 65.0 17,057
TOTAL SILVER5,768 18.5 3,43125,348 60.4 49,18531,116 52.6 52,616

Measured and Indicated Mineral Resources

MINERAL RESERVE AND MINERAL RESOURCE STATEMENT GOLD MEASURED AND INDICATED MINERAL RESOURCES (EXCLUDES PROVEN AND PROBABLE MINERAL RESERVES) (2,3,4,5,6,7,8) Kinross Gold Corporation's Share at December 31, 2017
PropertyLocationKinross InterestMeasuredIndicatedMeasured and Indicated
TonnesGradeOuncesTonnesGradeOuncesTonnesGradeOunces
(%)(kt)(g/t)(koz)(kt)(g/t)(koz)(kt)(g/t)(koz)
NORTH AMERICA
Bald MountainUSA100.0%21,8530.7465158,4850.62,884180,3380.63,349

Fort Knox

Area USA 100.0% 24,606 0.4 320 213,425 0.4 2,909 238,031 0.4 3,229

Round Mountain AreaUSA100.0%2,3780.430102,6830.72,363105,0610.72,393
SUBTOTAL48,837 0.5 815474,593 0.5 8,156523,430 0.5 8,971
SOUTH AMERICA
La Coipa 8Chile100.0%5,3051.83049,8491.959915,1541.9903
Lobo MarteChile100.0%96,6461.13,52588,7201.23,489185,3661.27,014
MaricungaChile100.0%35,9080.8937209,0970.74,492245,0050.75,429
ParacatuBrazil100.0%164,2860.31,530158,5410.31,719322,8270.33,249
SUBTOTAL302,145 0.6 6,296466,207 0.7 10,299768,352 0.7 16,595
AFRICA
ChiranoGhana90.0%3,0751.71667,9002.358010,9752.1746
TasiastMauritania100.0%4,9360.711369,6551.32,84674,5911.22,959
SUBTOTAL8,011 1.1 27977,555 1.4 3,42685,566 1.3 3,705
RUSSIA
DvoinoyeRussia100.0%---286.26286.26
KupolRussia100.0%758.92182611.229690111.0317
SUBTOTAL75 8.9 21854 11.0 302929 10.8 323
TOTAL GOLD359,068 0.6 7,4111,019,209 0.7 22,1831,378,277 0.7 29,594
MINERAL RESERVE AND MINERAL RESOURCE STATEMENT SILVER MEASURED AND INDICATED MINERAL RESOURCES (EXCLUDES PROVEN AND PROBABLE MINERAL RESERVES) (2,3,4,5,6,7,8) Kinross Gold Corporation's Share at December 31, 2017
PropertyLocationKinross InterestMeasuredIndicatedMeasured and Indicated
TonnesGradeOuncesTonnesGradeOuncesTonnesGradeOunces
(%)(kt)(g/t)(koz)(kt)(g/t)(koz)(kt)(g/t)(koz)
NORTH AMERICA
Round Mountain AreaUSA100.0%2,3788.76675,3096.81,1607,6877.41,827
SUBTOTAL2,378 8.7 6675,309 6.8 1,1607,687 7.4 1,827
SOUTH AMERICA
La Coipa 8Chile100.0%5,30537.16,3309,84974.023,44515,15461.129,775
SUBTOTAL5,305 37.1 6,3309,849 74.0 23,44515,154 61.1 29,775
RUSSIA
DvoinoyeRussia100.0%---286.05286.05
KupolRussia100.0%75126.4303826135.53,598901134.83,901
SUBTOTAL75 126.4 303854 131.3 3,603929 130.9 3,906
TOTAL SILVER7,758 29.3 7,30016,012 54.8 28,20823,770 46.5 35,508