Asanko Gold Mine Construction Update

Mine Development & Operations

Highlights:

  • Phase  1  construction  43%  complete  and  on  schedule  for  first  gold  in  Q1  2016.
  • Mining  activities  at  Nkran  pit  commenced  in  February  and  now  operating  24hrs/day
  • Pit  dewatering  on  track,  water  levels  reduced  by  approximately  11  metres.
  • Ball  and  SAG  mills  delivered  to  site,  ahead  of  schedule.
  • Project  spend  on  budget  with  US$214  million  of  the  US$295  million  capital  cost  committed.

Vancouver,  British  Columbia,  April  9,  2015  –  Asanko  Gold  Inc.  (“Asanko”  or  the  “Company”)  (TSX,  NYSE   MKT:  AKG)  is  pleased  to  provide  a  construction  update  on  its  fully  funded  Phase  1  project  of  the  Asanko Gold  Mine  (“AGM”  or  the  “Project”)  in  Ghana.    Phase  1  will  be  a  low  cost,  long  life  mine  producing  190,000 ounces  of  gold  per  annum  at  steady  state,  with  the  first  gold  pour  on  track  for  Q1  2016.

Project   construction   continues   to   advance   rapidly   and   is   on   schedule   with   43%   of   the   overall   project complete,  as  at  the  end  of  March  2015.  Plant  earthworks  are  nearing  completion  at  95%  and  concrete  civils at  41%  are  well  advanced.  Procurement  is  76%  complete.  US$67  million  has  been  spent  with  an  additional US$147   million   committed   out   of   the   total   capital   budget   of   US$295   million.   The   latest   videos   and photographs  are  available  at  http://www.asanko.com/projects/photo-­‐gallery.

Peter  Breese,  President  and  CEO,  commented:  “Phase  1  construction  is  proceeding  very  well.  We  are  nearly   half   way   through   the   build   and   currently   tracking   on   schedule   and   within   budget.   The   pre-­‐strip   mining   operations  are  well  underway,  with  first  ore  already  intercepted  and  being  stockpiled.  The  plant  site  is  also   taking  shape,  with  four  of  the  eight  tanks  in  the  carbon-­‐in-­‐leach  (“CIL”)  circuit  fully  erected.  It  is  pleasing  to   see   all   the   various   parts   of   the   construction   program   coming   together   with   the   process   plant   steel   and   platework  currently  being  installed.  Overarching  all  of  this  is  the  fact  that  we  have  now  worked  close  to  one   million  man-­‐hours  on  the  Project  without  a  lost  time  accident.    

The  Pre-­‐Feasibility  Study  (“PFS”)  on  Phase  2  is  nearing  completion  and  is  undergoing  internal  and  Board   reviews  prior  to  publication,  which  is  expected  in  early  May  2015.    The  PFS  will  outline  how  we  will  integrate   the   large,   adjacent   Esaase   deposit   into   Phase   1   to   create   a   world   class   mine   capable   of   producing   approximately  400,000  ounces  of  gold  per  annum  over  a  long  period  of  time.”  

Construction  Update  

The  concrete  pour  of  the  SAG  and  ball  mill  foundations  is  progressing  well.  The  pour  is  being  done  in  a series  of  “lifts”.  The  first  and  second  lifts  for  the  SAG  mill  have  been  completed  and  the  third  and  final  lift  is underway.    The  first  lift  for  the  ball  mill  has  been  completed  and  the  second  lift  is  due  for  completion  in April  2015.    The  SAG  and  ball  mills  have  been  delivered  to  site,  ahead  of  schedule,  and  installation  work  is due  to  commence  in  May  2015.

Erection  of  the  eight  tanks  for  the  CIL  circuit  is  underway.    Four  tanks  are  fully  erected,  with  welding  and painting   in   progress.   The   remaining   four   tanks   are   due   for   completion   during   May   2015.   The   pre-­‐leach thickener   base   has   been   completed   and   steel   erection   and   platework   are   progressing   well,   targeting completion  by  the  end  of  Q2  2015.    Work  has  also  commenced  on  the  reagents  building,  with  the  steelwork and  platework  expected  to  be  finished  during  May  2015.    The  foundations  for  the  Gold  Room  have  also been  completed.    The  electrical  and  Instrumentation  (“E&I”)  contract  has  been  awarded  and  the  contractor is  mobilizing  to  site,  in  readiness  to  start  with  E&I  installation  in  May  2015.

Casting  of  the  concrete  panels  for  the  run-­‐of-­‐mine  tip  wall  at  the  primary  crusher  is  nearing  completion  and construction  of  the  reinforced  earth  wall  has  commenced.  The  first  and  second  lift  of  the  stockpile  tunnel has  also  been  completed.

Progress  on  the  preparation  of  the  tailings  storage  facility  is  advancing  according  to  schedule  and  laydown of  the  HDPE  liner  commenced  in  March  2015.

The   Company   continues   to   advance   negotiations   for   a   definitive   power   supply   agreement   from   an independent  power  producer.    These  negotiations  are  expected  to  be  finalized  by  the  end  of  Q2  2015.  Bush clearing  and  ground  preparation  has  been  completed  on  82%  of  the  route  for  the  161  kV  line.  Foundation work  has  commenced  for  the  towers  as  well  as  the  medium  voltage  substation  at  the  project  site.

The  contractor  camp  housing  is  fully  functioning  and  accommodating  460  contractors.  There  are  now  over 1,000  contractor  personnel  on  site,  with  the  full  complement  of  1,400  contractors  expected  by  the  end  of Q3  2015.

Mining  

Pre-­‐stripping  of  the  Nkran  Pit,  the  main  mineral  resource  for  Phase  1,  is  advancing  well  with  two  excavators working  in  the  pit  on  a  24hr/day  operation,  the  third  excavator  is  scheduled  to  be  commissioned  in  April bringing   the   fleet   up   to   full   strength.   So   far   2   million   tonnes   of   waste   has   been   mined   in   the   first   two months  of  operations  and  approximately  1,700  ore  tonnes  have  been  identified  and  placed  on  the  run-­‐of-­‐ mine  pad  at  a  grade  of  2.7g/t.

The  pit  requires  21.7  million  tonnes  of  waste  to  be  pre-­‐stripped  prior  to  commencing  milling  operations  in Q1  2016.  Included  in  the  pre-­‐strip  is  a  planned  423,000  tonnes  of  ore  at  a  gold  grade  of  2.09  g/t  which  will be  stockpiled  ahead  of  plant  commissioning.

De-­‐watering  of  the  Nkran  pit  commenced  in  December  2014  and  by  the  end  of  March  1.67  million  of  the expected  6  million  cubic  metres  of  water  has  been  discharged  from  the  pit.  The  water  level  in  the  Nkran  pit has  reduced  by  approximately  11  metres.  The  de-­‐watering  is  on  schedule  and  expected  to  take  a  further  six months  to  complete.  De-­‐watering  will  continue  in  parallel  with  pre-­‐stripping  operations.

Health  and  Safety  

There  have  been  no  lost  time  accidents  on  site  with  315  days  of  construction  activity  and  928,091  man-­‐ hours  completed  on  the  project  to  date.  All  Safety,  Health  and  Environmental  systems  and  procedures  have been  fully  implemented  on  site.

Procurement  

Procurement  is  76%  complete  and  proceeding  on  schedule  with  approximately  US$214  million  currently committed  in  orders  and  contracts.  US$67  million  has  been  spent  as  at  March  31,  2015.  Equipment  and materials   deliveries,   none   of   which   are   on   the   project   critical   path,   remain   on   schedule.     Nearly   three-­‐ quarters  of  the  capital  expenditure  has  now  been  committed  and  the  Project  is  expected  to  be  completed within  the  US$295  million  capital  expenditure  budget.

Funding  

The  Company  is  fully  funded  to  cash  flow  positive  in  Q2  2016  with  approximately  US$224  million  in  cash  on-­‐ hand  as  at  March  31,  2015  and  undrawn  project  debt  facilities  of  US$70  million  plus  a  US$20  million  cost-­‐ overrun  facility  for  total  available  funding  of  approximately  US$314  million.  The  remaining  use  of  funds  is US$274  million  which  includes  US$228  million  for  the  project,  US$38  million  in  working  capital  and  US$8 million  in  corporate  costs  until  commercial  production  is  achieved.    The  Company  therefore  has  a  current funding  buffer  of  US$40  million.

Partial  Relocation  of  Nkran  Village  

A  portion  of  the  Nkran  village,  consisting  of  88  building  structures,  will  be  relocated  ahead  of  commencing ore  mining  operations.  The  site  for  the  relocation  was  selected  by  the  Relocation  Negotiation  Committee and  approved  by  the  Ghanaian  Lands  Commission.  Construction  commenced  in  February  2015  with  bulk earthworks   and   terracing.     The   buildings   tenders   have   been   awarded   and   the   construction   of   the   new houses  is  underway  with  10  local  contractors  having  been  selected  to  build  the  houses.    The  relocation  is expected  to  be  completed  by  the  end  of  Q3  2015.

Enquiries:  

For  further  information  please  visit:  www.asanko.com,  email:  [email protected]  or  contact:

Alex  Buck,  Manager  –  Investor  Relations   Wayne  Drier  -­‐  Executive,  Corporate  Development Toll-­‐Free  (N.America):  1-­‐855-­‐246-­‐7341   Telephone:  +1-­‐778-­‐729-­‐0614 Telephone:  +44-­‐7932-­‐740-­‐452   Email:  [email protected] Email:  [email protected]

About  Asanko  Gold  Inc.  

Asanko’s  vision  is  to  become  a  mid-­‐tier  gold  mining  company  that  maximizes  value  for  all  its  stakeholders. The  Company’s  flagship  project  is  the  multi-­‐million  ounce  Asanko  Gold  Mine  located  in  Ghana,  West  Africa. The  mine  is  being  developed  in  phases.  Phase  1  is  fully  financed,  permitted  and  under  construction.    First gold  is  expected  in  Q1  2016,  with  steady  state  production  of  190,000  ounces  per  annum  in  Q2  2016.

Asanko  is  managed  by  highly  skilled  and  successful  technical,  operational  and  financial  professionals.  The Company   is   strongly   committed   to   the   highest   standards   for   environmental   management,   social responsibility,  and  health  and  safety  for  its  employees  and  neighbouring  communities.

Forward-­‐Looking  and  other  Cautionary  Information

This   release   includes   certain   statements   that   may   be   deemed   "forward-­‐looking   statements".   All   statements   in   this   release,  other  than  statements  of  historical  facts,  that  address  estimated  resource  quantities,  grades  and  contained   metals,  possible  future  mining,  exploration  and  development  activities,  are  forward-­‐looking  statements.  Although  the   Company  believes  the  forward-­‐looking  statements  are  based  on  reasonable  assumptions,  such  statements  should  not   be  in  any  way  construed  as  guarantees  of  future  performance  and  actual  results  or  developments  may  differ  materially   from  those  in  the  forward-­‐looking  statements.  Factors  that  could  cause  actual  results  to  differ  materially  from  those  in   forward-­‐looking   statements   include   market   prices   for   metals,   the   conclusions   of   detailed   feasibility   and   technical   analyses,  the  timely  renewal  of  key  permits,  lower  than  expected  grades  and  quantities  of  resources,  mining  rates  and   recovery  rates  and  the  lack  of  availability  of  necessary  capital,  which  may  not  be  available  to  the  Company  on  terms   acceptable  to  it  or  at  all.  The  Company  is  subject  to  the  specific  risks  inherent  in  the  mining  business  as  well  as  general   economic   and   business   conditions.   For   more   information   on   the   Company,   Investors   should   review   the   Company's   annual  Form  20-­‐F  filing  with  the  United  States  Securities  Commission  and  its  home  jurisdiction  filings  that  are  available   at  www.sedar.com.  

Neither  Toronto  Stock  Exchange  nor  the  Investment  Industry  Regulatory  Organization  of  Canada  accepts  responsibility   for  the  adequacy  or  accuracy  of  this  release.  

Cautionary  Note  to  U.S.  Investors  Regarding  Mineral  Reporting  Standards:  

Asanko  has  prepared  its  disclosure  in  accordance  with  the  requirements  of  securities  laws  in  effect  in  Canada,  which   differ  from  the  requirements  of  US  securities  laws.  Terms  relating  to  mineral  resources  in  this  press  release  are  defined   in  accordance  with  National  Instrument  43-­‐101  -­‐  Standards  of  Disclosure  for  Mineral  Projects  under  the  guidelines  set   out   in   the   Canadian   Institute   of   Mining,   Metallurgy,   and   Petroleum   Standards   on   Mineral   Resources   and   Mineral   Reserves.    The  Securities  and  Exchange  Commission  (the  “SEC”)  permits  mining  companies,  in  their  filings  with  the  SEC,   to  disclose  only  those  mineral  deposits  that  a  company  can  economically  and  legally  extract  or  produce.    Asanko  uses   certain  terms,  such  as,  “measured  mineral  resources”,  “indicated  mineral  resources”,  “inferred  mineral  resources”  and   “probable  mineral  reserves”,  that  the  SEC  does  not  recognize  (these  terms  may  be  used  in  this  press  release  and  are   included   in   the   public   filings   of   Asanko   which   have   been   filed   with   securities   commissions   or   similar   authorities   in   Canada).