Friday, October 16, 2026
MiningNewsTerminal
Friday, October 16, 2026 Admin

FVI.TO ·

Fortuna delivers robust PEA for Diamba Sud Gold Project in Senegal: After-tax IRR of 72% and NPV5% of US$563 million using US$2,750 per ounce

Economic Studies

NEWS RELEASE

Fortuna delivers robust PEA for Diamba Sud Gold Project in Senegal: After-tax IRR of 72% and NPV5% of US$563 million using US$2,750 per ounce

(All financial information contained herein are expressed in US dollars unless otherwise stated)

Vancouver, October 15, 2025: Fortuna Mining Corp. (NYSE: FSM | TSX: FVI) is pleased to report the results of the Preliminary Economic Assessment (PEA) prepared for the Diamba Sud Gold Project in Senegal.

The PEA supports robust project economics for the development of an open-pit mine and conventional carbon-in-leach (CIL) processing plant. At a gold price of $2,750 per ounce, the assessment unveils an after-tax NPV5% of $563 million, an IRR of 72 percent, and a payback period of ten months. During the first three years of production, Diamba Sud is projected to deliver an average of 147,000 ounces of gold per year at an All-In Sustaining Cost1 (AISC) of $904 per ounce.

Construction capital cost is estimated at approximately $283.2 million. Project funding is derisked by the strength of Fortuna’s balance sheet and robust cash flow generation. As of the end of the second quarter of 2025, Fortuna reported liquidity of $537.3 million and a net cash position of $214.8 million. Jorge A. Ganoza, President and CEO at Fortuna, commented, “The PEA highlights the strong value Diamba Sud brings to Fortuna’s portfolio, using a long-term gold price of $2,750 per ounce. With permitting and the Definitive Feasibility Study underway, we expect to make a construction decision in the first half of 2026.” Mr. Ganoza continued, “Ongoing exploration is advancing with five drill rigs focused on expanding open areas of mineralization and to upgrade the small portion of Inferred Mineral Resources to the Measured and Indicated categories by year-end. With continued exploration success, we expect to enhance Diamba Sud’s life of mine production profile beyond a decade.” Mr. Ganoza concluded, “Additionally, we have approved a $17 million budget to advance early construction works, including the expansion of camp and ancillary facilities, as well as detailed engineering activities.”

Note:

1. This is a non-GAAP financial measure. The definition and purpose of this non-GAAP financial measure is included under the heading “Cautionary Note on Non-GAAP Measures” in this news release.

PEA Key Highlights

Table 1 summarizes the key assumptions, operational parameters, economic results, and AISC values from the PEA.

Table 1: PEA key highlights

Metrics Units Results

Gold price $/oz 2,750 Life of mine year 8.1 Total mineralized material mined1 Mt 17.75 Contained gold in mined resource1 koz 932 Strip ratio w:o 5.5:1 Throughput initial 3 years (oxide) Mtpa 2.5 Throughput @ nameplate (fresh) Mtpa 2.0 Head grade g/t Au 1.63 Recoveries % 90%

Gold production

Total Production over LOMkoz840
Average annual production, LOMkoz106
Average annual production, first 3 yearskoz147

Per unit costs over LOM

Total mining costs$/t, mined$4.82
Processing$/t, processed$13.91
G&A$/t, processed$6.70

Cash costs1

Average operating cash costs2, LOM $/oz $1,081 Average operating cash costs2, first 3 years $/oz $759

AISC1

Average AISC2, LOM $/oz $1,238 Average AISC2, first 3 years $/oz $904

Capital costs

Initial capital expenditure$ M$283
Sustaining capital, operations + Infrastructure(includes closure costs)$ M$48
NPV5%, pre-tax(100% project basis)$M$772
Pre-tax IRR%86%
NPV5%, after-tax(100% project basis)$M$563
After-tax IRR%72%
Payback periodyear0.8

Annual EBITDA 2 Average EBITDA2 over LOM $ M $167 Average EBITDA2 over first 3 years $ M $277

Notes:

1. The pit optimization shells used for the mining inventory were generated using a gold price of $2,300 per ounce.

2. This is a non-GAAP financial measure. The definition and purpose of this non-GAAP financial measure is included under the heading “Cautionary Note on Non-GAAP Measures” in this news release. Non-GAAP financial measures have no standardized meaning under IFRS and therefore, may not be comparable to similar measures presented by other issuers.

3. Average operating cash costs and average AISC represent costs for projected production for the LOM at the time of gold sales.

4. The PEA is presented on a 100 percent project basis. However, upon the granting of the exploitation permit, the Senegalese Government will be entitled to a 10 percent free-carried interest in the Project, with the right for the State to acquire an additional contributory interest of up to 25 percent.

5. The economic analysis was carried out using a discounted cash flow approach on a pre-tax and after-tax basis, based on the gold price of $2,750/oz.

-2-

6. The IRR on total investment that is presented in the economic analysis was calculated assuming a 100% ownership in Diamba Sud.

7. The NPV was calculated from the after-tax cash flow generated by the Project, based on a discounted rate of 5% and an effective date of October 10, 2025.

8. The PEA assumes that the percentage of certain royalties and taxes payable to the State, the percentage of the investment tax credit available to the company and the percentage payable to the social development fund will be in accordance with the provisions of the Mining Convention between Boya S.A. and the State of Senegal dated April 8, 2015. There can be no assurance that such provisions will not be renegotiated by the State as part of the exploitation permit approval process.

9. The PEA is preliminary in nature, and it includes inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves, and, as such, there is no certainty that the PEA results will be realized.

Exploration Upside: Resource Delineation and Exploration Drilling

Opportunities exist to further strengthen and enhance Diamba Sud’s economic foundation through continued drilling, resource extension testing, and definition of new targets. Successful exploration programs are expected to extend the Life of Mine (LOM) gold production profile to beyond a decade. Exploration drilling completed since the data cut-off for the Mineral Resource estimate in the PEA comprises 125 drill holes totaling 15,794 meters. Results from this recent drilling include drill hole DSDD488 that intersected 22.7 g/t Au over an estimated true width of 21.6 meters, highlighting substantial exploration upside (refer to Fortuna news release dated August 13, 2025: “Fortuna drills 22.7 g/t gold over 21.6 meters at Southern Arc, Diamba Sud Gold Project, Senegal”).

Exploration programs for the second half of 2025 are focused on:

  • Infill drilling at Area A, Area D, Karakara, Moungoundi, and Southern Arc to convert Inferred Resources to Indicated Resources in support of the forthcoming Definitive Feasibility Study (DFS) and Mineral Reserve estimate.
  • Step-out and resource expansion drilling at Southern Arc aimed at increasing the Mineral Resource and enhancing the LOM gold-production profile from year four onward.
  • Testing prospective targets identified across the broader Diamba Sud tenement package, which offer additional growth potential.
  • Continuing exploration at Fortuna’s Bondala properties, adjacent to Diamba Sud, where geophysical surveys and auger drilling have identified anomalies to be followed up with targeted drill programs.

Diamba Sud PEA Overview

The PEA outlines the design of an open pit gold mining operation targeting a series of deposits including Area A, Area D, Karakara, Western Splay, Kassassoko, Moungoundi, and Southern Arc which will feed a central gold processing facility over the current 8.1-year LOM. The assessment is based on Diamba Sud´s Mineral Resource estimate, which comprises an Indicated Mineral Resource of 14.2 million tonnes (Mt) at an average gold grade of 1.59 grams per tonne (g/t), containing 724,000 ounces of gold, and an Inferred Mineral Resource of 6.2 Mt at an average grade of 1.44 g/t gold, containing 285,000 ounces of gold, reported as of July 7, 2025 (refer to Fortuna news release dated August 5, 2025, “Fortuna Advances Diamba Sud Gold Project in Senegal with Updated Mineral Resources; PEA Completion Targeted for Q4 2025”).

-3-

Mining and Processing

The PEA and mine plan outline the design of an open pit gold mining operation feeding a central gold processing facility over the 8.1-year LOM. The assessment anticipates the concurrent development of multiple deposits, including Area A, Area D, Karakara, Western Splay, Kassassoko, Moungoundi, and Southern Arc, with no more than three pits mined at any one time (refer to Figure 1).

The production strategy targets an initial throughput of 2.5 million tonnes per annum (Mtpa) during the first three years of operation, supported by the high oxide content at Area D, before transitioning to a sustained rate of 2.0 Mtpa from year four onward as the feed becomes predominantly fresh material.

Exploration drilling completed at the Southern Arc deposit subsequent to the Mineral Resource estimate in the PEA has intersected near-surface mineralization to the south and east of the currently defined pit limits. It is anticipated that these results will be incorporated in future evaluations to enhance gold production in the later years of the LOM.

The pit optimization shells used to define the mining inventory were generated using a gold price of $2,300 per ounce and a revenue factor of 1.0. Optimization parameters incorporated government royalties, refining, mining, processing, and general and administrative costs to ensure realistic pit designs and economic assumptions.

-4-

Area A

Area D

Karakara

200 Kassasoko

Moungoundi

Southern Arc

Western Splay

Gold Production

Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8

Life of Mine

Figure 1: Diamba Sud PEA Production Profile: Annual gold production profile over the projected LOM, highlighting the contribution from individual deposits and the transition from oxide to fresh material.

Mining activities at Diamba Sud will employ conventional open pit methods. Drilling and blasting are planned for both oxide and fresh mineralized material, followed by conventional truck-and-shovel operations for the movement of potentially mineralized material and waste within the pits.

The Diamba Sud process plant design is based on a metallurgical flowsheet developed to produce gold doré at optimum recovery while minimizing initial capital and operating costs. The flowsheet comprises conventional crushing, milling (single-stage semi-autogenous grinding mill in closed circuit with cyclones), gravity recovery, carbon-in-leach processing, carbon elution, and gold recovery. A summary of the key operating and production statistics from the PEA is presented in Table 2.

-5-

Table 2: Diamba Sud LOM Mining and Processing Plan Metrics

UnitYear -1Year 0Year 1Year 2Year 3Year 4Year 5Year 6Year 7Year 8LOM
Area A
Potentially mineralizedkt91229232,0443,098
material mined
Au gradeg/t1.170.971.841.451.54
Area D
Potentially mineralizedkt691,8701,7181,6665,323
material mined
Au gradeg/t0.872.511.331.411.76
Karakara
Potentially mineralizedkt219741,7452,741
material mined
Au gradeg/t1.971.871.831.84
Kassassoko
Potentially mineralizedkt-301,0991,130
material mined
Au gradeg/t-1.040.970.97
Moungoundi34.3
Potentially mineralizedkt499296795
material mined
Au gradeg/t0.951.281.07
Southern Arc15.2
Potentially mineralizedkt01,5321,0082992643,103
material mined
Au gradeg/t0.471.581.681.651.981.65
Western Splay16.8
Potentially mineralizedkt1211,1722701,564
material mined
Au gradeg/t1.121.453.221.73
Total
Potentially mineralizedkt902,8453,5852,8471,9251,9312,3731,86229617,754
material mined
Au gradeg/t1.132.291.561.431.771.761.471.111.281.63
Contained goldkoz3.3209.4180.3130.5109.6109.0111.966.312.2932.4
Waste minedkt2,32216,32615,58816,38017,16613,7937,2647,59765697,092
Total minedkt2,41219,17119,17319,22819,09115,7239,6379,459953114,846
Stockpile
Start of periodkt905801,6652,0131,7121,5321,8751,524n/a
Gradeg/t1.130.760.570.590.680.590.590.58n/a
Processing
Material milledkt2,3542,5002,5002,2252,1112,0302,2131,82117,754
Head gradeg/t2.622.041.531.551.721.621.030.701.63
Contained goldkoz198.5163.8122.7110.8117.0105.773.240.7932.4
Recovery%92.592.186.188.290.091.987.986.690.1
Gold productionkoz183.7150.9105.697.7105.397.264.335.3840

-6-

Tailings, Water and Power

The tailings management system will comprise a tailings pipeline and a water return pipeline housed within a geomembrane-lined trench, with associated tailings pumps. The Tailings Storage Facility (TSF) will be fully lined with a geomembrane and will be developed as a side-valley storage facility formed by robust, multi-zoned earth-fill embankments. It is designed to accommodate 17.8 Mt of tailings and will be constructed using the downstream methodology, in accordance with industry best practices and the Global Industry Standard on Tailings Management (GISTM).

A water storage dam will serve as the main collection and storage facility for clean, raw, and process water. Raw water is currently assumed to be supplied via a pipeline from the Falémé River, supplemented by pit dewatering activities. Ongoing studies are evaluating the potential to develop a water harvesting facility as an alternative source. Process water from the TSF will be recycled back to the plant, with site operations designed as a closed-circuit system to maximize water reuse and minimize environmental impacts on surrounding communities.

Power for Diamba Sud is expected to be self-supplied through an on-site power plant. The current plan envisages a heavy fuel oil power plant constructed in an N+1 configuration, supported by light fuel oil generators to meet site-wide demand. In parallel, a hybrid solar photovoltaic system is being evaluated as part of the preparation of the DFS.

Capital Costs Summary

The PEA estimates the total initial capital required to develop Diamba Sud to be $283.2 million, including $4.0 million in capitalized closure costs to be deposited into escrow and a $46.4 million contingency. Sustaining capital is estimated at an additional $40.0 million, directly related to mining operations, processing, and infrastructure sustaining capital, along with a further $8.0 million in closure costs over the 8.1-year LOM.

Mining pre-production capital includes all mining activities required prior to commissioning of the processing facility. A total of 2.3 Mt of waste and 90 kt of potentially mineralized material will be mined to establish a stockpile ahead of processing operations. All contractor mobilization and setup costs are included in the pre-production capital allowance.

The processing plant capital estimate relates to a facility with a nameplate throughput of 2.0 Mtpa, designed to accommodate up to 2.5 Mtpa. The capital cost estimate is based on an Engineering, Procurement, Construction, and Management (EPCM) implementation approach.

A summary of estimated capital costs is presented in Table 3, and the estimated annual sustaining capital costs are set out in Table 4.

-7-

Table 3: Summary of Initial Development Capital Costs

Capital CostsValue ($ M)
Construction costs Pre-production costs (excluding mining) Mining pre-stripping Contingency Withholding taxes, duties, levies$191.7
$21.6
$19
$46.4
$4.5
Total$283.2

Table 4: Estimated Annual Sustaining Capital Costs

YearUnitsYearYearYearYearYearYearYearYearYearYearTotal
12345678910
TSF lifts $ M4.5-7.3-11.7-11.1-34.6
Roads $ M-2.10.2--0.10.3-2.7
Surface water $ M management-1.00.9---0.3-2.3
Closure $ M--0.60.60.60.60.65.38.5
Total $ M4.53.19.10.612.30.712.45.348.0

-8-

Operating Costs Summary

The PEA estimates direct operating costs of $51.16 per tonne of material milled or $1,081 per ounce of gold produced, and AISC1 of $1,238 per ounce over the LOM, as summarized in Table 5.

Table 5: LOM AISC1

$M $/t milled $/payable oz

Operating cost

Mining54230.54646
Processing24713.91294
G&A1196.70142
Subtotal, direct operating costs90851.161,081
Refining30.143
Royalties2693.9083
Social Development Fund2120.6514
Total Operating Costs99255.851,180

Sustaining Capital, and Reclamation

Sustaining Capital402.2347
Closure80.4810
All-in Sustaining Cost11,04058.561,238

Notes:

1. AISC and cash costs per payable ounce of gold sold are non-GAAP financial measures; refer to “Cautionary Note on Non-GAAP Measures”

2. The PEA assumes a 3% royalty payable to the State and 0.5% contribution to a Social Development Fund

-9-

Financial Analysis

Diamba Sud has been evaluated on a discounted cash flow basis and the results of the PEA demonstrate that it is potentially economically robust. The base case, using a gold price of $2,750 per ounce, generates an after-tax NPV at a 5 percent discount rate of $563 million, an IRR of 72 percent, and a payback period of approximately ten months. Figure 2 illustrates the estimated cash flow profile of Diamba Sud over the LOM.

Figure 2: Diamba Sud Cash Flow Profile

Sensitivity Analysis: Strong economic performance across a range of key variables

Diamba Sud´s NPV and IRR are most sensitive to changes in revenue parameters, including gold price, head grade, and process plant recovery. NPV and IRR are more sensitive to variations in operating costs than to capital costs.

Estimated NPV sensitivities for key operating and economic metrics are presented in Figure 3.

-10-

Figure 3: After-tax NPV5% Sensitivities

The sensitivity of Diamba Sud’s NPV to changes in the applied discount rate and gold price is presented in Table 5; base case highlighted.

Table 5: Gold Price and Discount Rate Sensitivities on Post-tax NPV ($ M)

Gold Price ($/oz)
$2,000$2,250$2,500$2,750$3,000$3,250$3,500$3,750
Discount3.0$230$362$494$622$750$878$1,007$1,134
Rate (%)5.0$200$322$444$563$682$800$919$1,037
7.0$173$287$400$511$621$731$841$951

-11-

The sensitivity of Diamba Sud’s IRR to changes in the key operating parameters is illustrated in Figure 4.

IRR Figure 4: Diamba Sud Post-Tax IRR sensitivities

Environmental and Permitting

On October 6, 2025, Fortuna filed an Environmental and Social Impact Assessment (ESIA) with the Direction de la Réglementation Environnementale et du Contrôle (DiREC), a division of the Ministry of the Environment and Sustainable Development of Senegal (refer to Fortuna news release dated October 7, 2025, “Fortuna Files Environmental and Social Impact Assessment for the Diamba Sud Gold Project in Senegal and provides update on Preliminary Economic Assessment status”). The filing of the ESIA marks an important milestone in the permitting process.

Fortuna expects to apply and receive an exploitation permit for Diamba Sud before the expiry of its exploration permit in June 2026.

Next Steps: Definitive Feasibility Study and Early Works

Fortuna has approved a supplementary budget of $17 million to de-risk Diamba Sud’s development schedule by advancing early work planning and permitting in parallel with early works construction activities to establish site access and a new accommodation camp. In addition, subject to Board approval, front-end engineering and design is scheduled to commence this quarter, followed by the procurement of long-lead items in the second quarter of 2026 to ensure readiness for project execution. The DFS is expected to be completed towards the end of the second quarter of 2026, leading to an anticipated construction decision shortly thereafter. A positive construction decision would position Diamba Sud to begin full construction in the fourth quarter of 2026, following the wet season, with first gold pour targeted for the second quarter of 2028.

-12-