Wednesday, October 21, 2026
MiningNewsTerminal
Wednesday, October 21, 2026 Admin

AG.TO ·

FR Frankfurt – FMV First Majestic Announces 2020 Production and Cost Guidance

Production Results

FIRST MAJESTIC SILVER CORP.

Suite 1800 – 925 West Georgia Street Vancouver, B.C., Canada V6C 3L2 Telephone: (604) 688-3033 Fax: (604) 639-8873 Toll Free: 1-866-529-2807 Web site: www.firstmajestic.com; E-mail: [email protected]

NEWS RELEASE

New York – AG                January 21, 2020 Toronto – FR Frankfurt – FMV

First Majestic Announces 2020 Production and Cost Guidance

Vancouver, BC, Canada ‐ First Majestic Silver Corp. ("First Majestic" or the "Company") is pleased to announce the Company’s 2020 production and cost guidance including capital investments and future growth initiatives. All amounts are in U.S. dollars unless stated otherwise.

“For 2020, our focus remains on adopting new innovation projects to modernize our processing plants to achieve  higher recoveries, improve efficiencies and reduce operating costs,” said Keith Neumeyer, President & CEO. “We  have witnessed significant benefits from high‐intensity grinding at our Santa Elena operation in 2019 and we plan  to  install  the  same  technology  at  San  Dimas  in  2020.  In  addition,  we  continue  to  advance  underground  development activities at the Ermitaño project near Santa Elena to prepare the mine for initial production in early  2021. Our increased investments in underground development and innovation in 2020 is expected to result in  significant production growth in 2021 and beyond.”

The Company expects 2020 silver production to range between 11.8 to 13.2 million ounces with total production (including gold by‐products) between 21.5 to 24.0 million silver equivalent ounces. The Company’s guidance only assumes production coming from its three largest mines: the San Dimas, Santa Elena and La Encantada mines. The San Martin and La Parrilla mines are expected to remain suspended throughout 2020 and the Del Toro mine is being wound down with no production in 2020.  By suspending the Company’s highest cost lead and zinc mines, management is now able to focus all of its efforts on cost reduction and innovation at its most profitable silver and gold mines.

2020 Production and Cost Guidance Highlights

  • The Company plans to increase production at San Dimas by restarting mining operations at the past‐ producing Tayoltita mine by the end of the first quarter and expects to ramp up production to 300 tpd by the end of 2020. The Tayoltita mine was the original mining area at San Dimas and known to contain higher silver grades. In addition, the Company plans to install a new 3,000 tpd high‐intensity grinding (“HIG”) mill circuit and an autogenous (“AG”) grinding mill in the second half of 2020 to further improve recoveries and reduce operating costs.
  • Silver production at La Encantada is expected to increase to between 2.9 to 3.3 million ounces due to continued improvements in metallurgical recoveries and grades from the San Javier and La Prieta sub‐

level caving areas. Furthermore, the Company is preparing to bring the Milagros breccia into production in the fourth quarter of 2020.

  • The Company expects higher silver production at Santa Elena due to improved metallurgical recoveries from the recently installed HIG mill.  The Company also plans to install an autogenous/semi‐autogenous (“AG/SAG”) grinding mill by the end of 2020 and plans to implement a dual‐circuit flowsheet to separate the ultra‐fine and  coarse  particles prior to leaching to further improve  metallurgical recoveries and reduce energy costs.  Additionally, the Company plans to convert power generation at Santa Elena from diesel to liquid natural gas in the fourth quarter of 2020.
  • The San Martin mine is expected to remain in temporary suspension throughout 2020 due to security concerns  as  previously  announced  in  the  Company's  news  release  on  July  15,  2019.  The  Company continues to work with authorities to secure the area but there is no indication of when a restart of the operation might occur.
  • Following  an  extensive  review  of  the  Del  Toro  operation,  the  Company  has  decided  to  temporarily suspend  mining  and  milling  operations  in  2020  in  order  to  improve  operating  cash  flow  and  profit margins while focusing on an expanded drill program in the area.  This expanded program will include approximately 22,450 metres of drilling to test near mine targets in an effort to develop new resources necessary  to  support  a  potential  reopening  in  the  future,  subject  to  a  sufficient  improvement  in economics to justify a restart. In the meantime, the Company will continue evaluating mining methods and  metallurgical  testwork  on  the  San  Juan  orebody  which  contains  a  large  zinc  mineral  resource. Additionally,  the  Company  will  continue  supporting  CSR  projects  and  activities  to  assist  local stakeholders and partners in the communities surrounding the La Parrilla and Del Toro mines. The Del Toro mine produced 493,636 silver equivalent ounces which accounted for approximately 2% of the Company’s total production in 2019.

A mine‐by‐mine breakdown of the 2020 production guidance is included in the table below. Cash cost and all‐in sustaining cost per ounce (“AISC”) guidance is shown per payable silver ounce. Metal price and foreign currency assumptions for calculating equivalents are: silver: $17.00/oz, gold: $1,450/oz, MXN:USD 19:1.

MineSilver Oz (M)Gold Oz (k)Silver Eqv Oz (M)Cash Costs ($)AISC ($)
San Dimas6.5 – 7.281 – 9013.4 – 14.92.47 – 3.628.28 – 10.10
Santa Elena2.4 – 2.733 – 365.2 – 5.86.67 – 8.299.80 – 11.77
La Encantada2.9 – 3.3–2.9 – 3.312.27 – 13.2914.96 – 16.29
Totals:11.8 – 13.2114 – 12621.5 – 24.0$5.76 – $6.97$13.37 – $15.46

*Certain amounts shown may not add exactly to the total amount due to rounding differences.

*Consolidated AISC includes Corporate General & Administrative cost estimates and non‐cash costs of $2.61 to $2.90 per payable silver ounce.

The Company is projecting its 2020 AISC, as defined by the World Gold Council, to be within a range of $13.37 to $15.46 on a per consolidated payable silver ounce basis. Excluding non‐cash items, the Company anticipates its 2020 AISC to be within a range of $12.54 to $14.53 per payable silver ounce. An itemized AISC cost table is provided below:

FY 2020             All‐In Sustaining Cost Calculation (1)

($ /Ag oz) 

Total Cash Costs per Payable Silver Ounce (2)  5.76 – 6.97 General and Administrative Costs  1.78 – 1.98 Sustaining Development Costs  2.09 – 2.33 Sustaining Property, Plant and Equipment Costs  1.88 – 2.10 Sustaining Exploration Costs  0.04 – 0.04 Profit Sharing  0.60 – 0.66 Lease Payments  0.40 – 0.45 Share‐based Payments (non‐cash)  0.65 – 0.72 Accretion of Reclamation Costs (non‐cash)  0.18 – 0.20

All‐In Sustaining Costs: (WGC definition)   $13.37 – $15.46 All‐In Sustaining Costs: (WGC excluding non‐cash items)  $12.54 – $14.53

1. AISC is a non‐GAAP measure and is calculated based on guidance provided by the World Gold Council (“WGC”) in June 2013. AISC is used as a comprehensive measure for the Company’s consolidated operating  performance.  WGC  is  a  not  a  regulatory  industry  organization  and  does  not  have  the authority to develop accounting standards for disclosure requirements.  Other mining companies may  calculate  AISC  differently  as  a  result  of  differences  in  underlying  accounting  principles,  the definition of “sustaining costs” and the distinction between sustaining and expansionary capital costs.

2. Total cash cost per payable silver ounce includes estimated royalties and 0.5% mining environmental fee of $0.10 per ounce.

Innovation Remains a Key Focus in 2020  

As a result of significant improvements in metallurgical recoveries at Santa Elena following the installation of the 3,000 tpd HIG mill circuit in 2019, the Company has elected to install HIG mill technology at its San Dimas and La Encantada mines in 2020 and 2021, respectively.

At San Dimas, the Company plans to install a new 3,000 tpd HIG mill circuit in 2020 to further improve recoveries and reduce operating costs. The delivery of the HIG mill is expected in the first quarter of 2020 followed by installation and commissioning in the second half of 2020. Furthermore, milling at San Dimas will be converted into a single AG grinding mill thereby eliminating the use of the three standard ball mills currently in operation. This  AG  conversion  is  expected  to  reduce  energy  consumption,  eliminate  steel  grinding  media,  improve metallurgical recoveries and streamline maintenance and mill practices.

At Santa Elena, the Company plans to implement a dual‐circuit flowsheet to separate the ultra‐fine and coarse particles prior to leaching to further improve metallurgical recoveries and reduce operating costs. Separating the different  sized  particles  allows  for  more  effective  use  of  available  retention  time,  decreased  reagent consumption and improved filtration circuit performance.  Additionally, a new AG/SAG mill circuit is expected to be commissioned by the end of 2020.

At La Encantada, the Company plans to invest in several plant modernizations in 2020 intended to improve processing efficiencies including, but not limited to: upgrading the tailings filter presses and belt conveyors; replacing the main gear and rakes for two thickeners; as well as completing the detailed engineering design in the second half of 2020 for a new 3,000 tpd HIG mill circuit, which is expected to be installed and commissioned in 2021.

Capital Investments for Future Growth 

In 2020, the Company plans to invest a total of $171.5 million on capital expenditures consisting of $52.6 million for  sustaining  investments  and  $118.9  million  for  expansionary  projects.  This  represents  a  24%  increase compared  to  the  revised  2019  capital  budget  and  is  aligned  with  the  Company’s  future  growth  strategy  of investments  in  HIG  mill  technology,  processing  plant  modernizations  and  underground  development  of  the Ermitaño project to prepare the mine for production in early 2021.

The  2020  annual  budget  includes  total  capital  investments  of  $62.9  million  to  be  spent  on  underground development; $32.9 million towards property, plant and equipment; $28.2 million in exploration; and $47.5 million towards corporate automation and efficiency projects. Additionally, the Company has been working on reducing its general and administration costs to rightsize the business due to the suspension of operations at Del Toro and La Parrilla. Management may revise the guidance and budget during the year to reflect actual and anticipated changes in metal prices or to the business.

The Company plans to complete a total of approximately 38,650 metres of underground development in 2020 compared with 54,517 metres completed in 2019. This 29% decrease is primarily due to the recent suspension of mining activities at the San Martin, La Parrilla and Del Toro mines. The 2020 development program consists of approximately 23,750 metres at San Dimas; 6,100 metres at Santa Elena; 4,450 metres at La Encantada; 3,800 metres at the Ermitaño project near Santa Elena; and 550 metres at Del Toro.

The Company also plans to complete approximately 192,900 metres of exploration drilling in 2020 compared to 204,371 metres completed in 2019. The 2020 drilling program consists of approximately 84,750 metres at San Dimas intended to add new mineral resources with a focus on the West, Central, and Tayoltita blocks; 30,500 metres at Santa Elena to continue exploring the Main and America veins and test greenfield targets around Los Hernandez; 21,200 metres at La  Encantada with an emphasis on exploring the  mineral potential of several brownfield targets; 15,000 metres at the Ermitaño project intended to increase resource confidence and add new mineral resources; and 22,450 metres at Del Toro and 19,000 metres at La Parrilla intended to test new brownfield and near mine targets.

Mr. Ramon Mendoza Reyes, Vice President Operations and Technical Services for First Majestic, is a "Qualified Person" as such term is defined under National Instrument 43‐101, and has reviewed and approved the technical information disclosed in this news release.

Conference Call 

The Company will be holding a conference call and webcast today, January 21, 2020 at 8:00 am PT (11:00 am ET) to  discuss  the  quarterly  production  results  as  well  as  its  2020  production,  cost  and  capital  guidance.  To participate in the conference call, please dial the following:

Toll Free Canada & USA:   1‐800‐319‐4610  Outside of Canada & USA:  1‐604‐638‐5340  Toll Free Germany:   0800 180 1954  Toll Free UK:   0808 101 2791 

Participants should dial in 10 minutes prior to the conference.

Click on WEBCAST on the First Majestic homepage as a simultaneous audio webcast of the conference call will be posted at www.firstmajestic.com.

The conference call will be recorded and you can listen to an archive of the conference by calling:

Canada & USA Toll Free:  1‐800‐319‐6413  Outside Canada & USA:   1‐604‐638‐9010 

Access Code:     3930 followed by the # sign 

The replay will be available approximately one hour after the conference and will available for 7 days following the conference.  The replay will also be available on the Company’s website for one month.

About the Company 

First Majestic is a mining company focused on silver production in Mexico and is aggressively pursuing the development of its existing mineral property assets. The Company presently owns and operates the San Dimas Silver/Gold Mine, the Santa Elena Silver/Gold Mine and the La Encantada Silver Mine. Production from these mines are projected to be between 11.8 to 13.2 million silver ounces or 21.5 to 24.0 million silver equivalent ounces in 2020.

FOR FURTHER INFORMATION contact [email protected], visit our website at www.firstmajestic.com or call our toll free number 1.866.529.2807.

FIRST MAJESTIC SILVER CORP.

"signed"

Keith Neumeyer, President & CEO

Cautionary Note Regarding Forward Looking Statements

This  press  release  contains  “forward‐looking  information”  and  "forward‐looking  statements”  under  applicable  Canadian  and  U.S.  securities  laws (collectively,  “forward‐looking  statements”).  These  statements  relate  to  future  events  or  the  Company's  future  performance,  business  prospects  or opportunities that are based on forecasts of future results, estimates of amounts not yet determinable and assumptions of management made in light of management's experience and perception of historical trends, current conditions and expected future developments. Forward‐looking statements include, but are not limited to, statements with respect to: the Company’s business strategy; future planning processes; commercial mining operations; cash flow; budgets; the timing and amount of estimated future production; recovery rates; mine plans and mine life; the future price of silver and other metals; costs of  production;  costs  and  timing  of  the  development  of  new  deposits;  capital  projects  and  exploration  activities  and  the  possible  results thereof. Assumptions may prove to be incorrect and actual results may differ materially from those anticipated. Consequently,  guidance cannot be guaranteed. As such, investors are cautioned not to place undue reliance upon guidance and forward‐looking statements as there can be no assurance that the plans, assumptions or expectations upon which they are placed will occur. All statements other than statements of historical fact may be forward‐ looking statements. Statements concerning proven and probable mineral reserves and mineral resource estimates may also be deemed to constitute forward‐looking statements to the extent that they involve estimates of the mineralization that will be encountered as and if the property is developed, and in the case of measured and indicated mineral resources or proven and probable mineral reserves, such statements reflect the conclusion based on certain assumptions that the mineral deposit can be economically exploited. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives or future events or performance (often, but not always, using words or phrases such as “seek”, “anticipate”, “plan”, “continue”, “estimate”, “expect”, “may”, “will”, “project”, “predict”, “forecast”, “potential”, “target”, “intend”, “could”, “might”, “should”, “believe” and similar expressions) are not statements of historical fact and may be “forward‐looking statements”.

Actual results may vary from forward‐looking statements. Forward‐looking statements are subject to known and unknown risks, uncertainties and other factors that may cause actual results to materially differ from those expressed or implied by such forward‐looking statements, including but not limited to:  risks  related  to  the  integration  of  acquisitions;  actual  results  of  exploration  activities;  conclusions  of  economic  evaluations;  changes  in  project parameters as plans continue to be refined; commodity prices; variations in ore reserves, grade or recovery rates; actual performance of plant, equipment or  processes  relative  to  specifications  and  expectations;  accidents;  labour  relations;  relations  with  local  communities;  changes  in  national  or  local governments; changes in applicable legislation or application thereof; delays in obtaining approvals or financing or in the completion of development or construction activities; exchange rate fluctuations; requirements for additional capital; government regulation; environmental risks; reclamation expenses;

outcomes of pending litigation; limitations on insurance coverage as well as those factors discussed in the section entitled "Description of the Business ‐ Risk Factors" in the Company's most recent Annual Information Form, available on www.sedar.com, and Form 40‐F on file with the United States Securities and Exchange Commission in Washington, D.C.  Although First Majestic has attempted to identify important factors that could cause actual results to differ materially from those contained in forward‐looking statements, there may be other factors that cause results not to be as anticipated, estimated or intended.

The Company believes that the expectations reflected in these forward‐looking statements are reasonable, but no assurance can be given that these expectations will prove to be correct and such forward‐looking statements included herein should not be unduly relied upon. These statements speak only as of the date hereof. The Company does not intend, and does not assume any obligation, to update these forward‐looking statements, except as required by applicable laws.