Thursday, October 22, 2026
MiningNewsTerminal
Thursday, October 22, 2026 Admin

ADE.V ·

Adex Reports Updated Mineral Resource Estimate for North Zone at Mount Pleasant

Resource Estimates Technical Reports (NI 43-101)

Toronto, Ontario – March 1, 2012 – Adex Mining Inc. (“Adex” or the “Company”) (TSX‐V: ADE) is pleased  to  announce  the  results    of  an  updated  National  Instrument  (“NI”)  43‐101  mineral resource  estimate  for  the  North  Zone  (“NZ”)  at  its  Mount  Pleasant  Mine  property  in  New Brunswick, Canada.

The updated mineral resource estimate includes 12,400,000 Indicated tonnes averaging 0.38% tin (“Sn”), 0.86% zinc (“Zn”), and 64 parts per million (ppm) indium (“In”).  Compared to the May 6, 2009 mineral resource estimate, this represents a 14% increase in Indicated tonnes using a cut‐off grade 64% higher than in the 2009 report. Contained metal in the Indicated category within the new mineral resource estimate is 47,000,000 kilograms (kg) of tin, 107,000,000 kg of zinc and 789,000 kg of indium. Compared to 2009, contained tin is approximately the same but contained zinc and indium have increased by 34,000,000 kg and 100,000 kg, respectively.

“These  are  exciting  results  that  further  strengthen  our  confidence  in  Mount  Pleasant,”  said Patrick Merrin, Chief Operating Officer for Adex.  “Our updated resource was calculated using a higher  cut‐off  grade  and  we  have  succeeded  in  reclassifying  a  portion  of  our  resource  from Inferred to Indicated. The 2010 and 2011 drill programs along with the metallurgical testing that we have completed has given us a much better understanding of how to extract the most value from this resource. ”

The updated mineral resource estimate also includes 2,800,000 Inferred tonnes averaging 0.30% tin, 1.13% zinc, and 70 ppm indium. Contained inferred metal from the new mineral resource estimate is 8,600,000 kg tin, 32,000,000 kg zinc and 198,000 kg indium.

Mineral resource and contained metal estimates are summarized below in Tables 1 and 2.

In  addition  to  the  known  tin‐zinc‐indium  resources  in  the  NZ,  the  results  of  the  2011  drill program confirmed and expanded the extent of the high‐grade tungsten‐molybdenum‐bismuth (WO3‐MoS2‐Bi) mineralization in the NZ and Saddle Zone with grades and widths similar to those being assessed at the Fire Tower Zone (“FTZ”) (News Release, Jan. 31, 2012).  A  follow‐up drill program is planned (News Release, Feb. 16, 2012) with the purpose of further expanding and amalgamating  the  WO3‐MoS2‐Bi  mineralized  bodies,  which  were  originally  part  of  the  initial 2009 NZ NI 43‐101 mineral resource estimate, with those in the FTZ.  This will be conducted in conjunction  with  the  preparation  of  an  updated  NI  43‐101  resource  estimate  and  feasibility study for all of the WO3‐MoS2‐Bi mineralized bodies at Mount Pleasant Mine.

RESULTS 

Table 1: February 2012 Mineral Resources – North Zone, Mount Pleasant Property 

Mineral ResourcesTonnageSn Grade, CutZn Grade, CutIn Grade, Cut
Class(Millions of tonnes)(%)(%)(ppm)
Indicated12.40.380.8664
Inferred2.80.301.1370

1. Resources were estimated using composites within a Block Model with block dimensions of 5x5x5m and using an inverse  distance  squared  grade  interpolation  method.  Top  cuts  were  applied  to  Sn,  Zn  and  In  assays  before compositing. A cut‐off of US$75 Gross Metal Value (“GMV”) was applied and a recovery of 100% is assumed;

2. Mineral resources which are not mineral reserves do not have demonstrated economic viability.  The estimate of mineral resources may be materially affected by environmental, permitting, legal, title, socio‐political, marketing, or other relevant issues;

3. The quantity and grade of reported inferred mineral resources in this estimation are uncertain in nature and there has been insufficient exploration to define these inferred resources as an indicated or measured mineral resource  and  it is  uncertain  if  further  exploration  will  result  in  upgrading  them  to  an  indicated  or  measured mineral resource category; and

4. The mineral resources in this press release were estimated using the Canadian Institute of Mining, Metallurgy and Petroleum (CIM), CIM Standards on Mineral Resources and Reserves, Definitions and Guidelines prepared by the CIM Standing Committee on Reserve Definitions and adopted by CIM Council November 27, 2010.

The contained metal within the new mineral resource estimate is:

Table 2: Contained Metal, North Zone Mount Pleasant Property (Capped*) 

Mineral Resources ClassContained Sn (kg,)Contained Zn (kg)Contained In (kg)
Indicated47,000,000107,000,000789,000
Inferred8,600,00032,000,000198,000

1. Top cuts of 3% Sn and 4% Sn were applied to Sn assays before compositing; top cuts of 5% Zn and 8% Zn were applied to Zn assays before compositing and top cuts of 500 ppm In and 600 ppm In were applied to In assays before compositing. The top cuts applied varied according to the domain. A cut‐off of US$75 GMV was applied and a recovery of 100% is assumed; and

2. Figures may not total due to rounding.

MINERAL RESOURCE STATEMENT 

The  updated  mineral  resource  estimates  have  been  prepared  on  behalf  of  Watts,  Griffis  and McOuat  Limited,  Consulting  Geologists  and  Engineers  of  Toronto  (“WGM”)  by  WGM  Senior Geological Associate John Reddick, M.Sc., P.Geo., of Reddick Consulting Inc. (“RCI”) and Mohan Srivastava, M.Sc., P.Geo., of FSS Canada Consultants Inc., all of whom are independent of Adex.

A total of 27,527 samples in 640 diamond drill holes, representing approximately 76,000 metres of  drilling,  were  used  for  the  estimate.  The  drilling  includes  underground  and  surface  holes completed from the 1950s through 2011. Of these, 81 drill holes from surface totalling 19,027 metres  were  completed  by  Adex  from  1996  to  2011.  The  mineral  resource  is  constrained  by wireframes  of  the  favourable  host  lithologies.    Domains  were  modelled  that  reflected  the different nature of the Sn, Zn and In mineralisation.  Metal grades were interpolated into 5‐by‐5‐ by‐5‐metre blocks using an inverse distance squared (ID2) estimation method.

Metal prices of US$8.33 per pound Sn, $0.91 per pound Zn, and $600.00 per kilogram for In, based on the three‐year trailing average, were used to estimate a combined Gross Metal Value (“GMV”) of US$75 to establish the cut‐off value for blocks.  The GMV of US$75 is equal to a Sn equivalent cut‐off grade of 0.41 wt%, which is 64% higher than the Sn equivalent cut‐off grade of 0.25 wt% Sn used in the initial NI 43‐101 resource estimate for the NZ completed in 2009. The  higher  cut‐off  was  chosen  based  upon  the  results  of  the  2010  Preliminary  Economic Assessment  completed  for  the  NZ  (filed  on  SEDAR),  which  estimated  total  operating  costs ranging from US$64 to $109 per tonne and identified Sn,  In and Zn as potentially economic extractable metals for the deposit.  In‐house data from Adex and technical data from Reddick Consulting Inc for similar deposits were also used to derive the cut‐off value.

Mineral resources were classified as Indicated in each domain if:

a) there were a minimum of six composites from at least two different holes available within the search ellipse for each block estimated; and

b) there were a minimum of two octants with samples available for each block estimated. Mineral resources were classified as Inferred if at least two composites were found within the search ellipse.  For both classes, the longest search direction was 35m and the shortest 20m. The search ellipse was determined from variography analyses and composites contributing to block grades were constrained by the wireframes.

Assay grades were composited to nominal 3‐m lengths prior to resource estimation. Unsampled intervals were included in the composites at nil grades. To date all samples have been tested for Sn  and  Zn,  while  only  34%  have  been  tested  for  In.  The  applied  methodology  provides  a conservation approach for the estimation of the In within the resource. Top cuts of 4% Sn, 5% Zn and 500 ppm In were applied for the Endogranite subzone (“100”) domain and top cuts of 3% Sn, 8% Zn and 600 ppm In were applied outside of the Endogranite subzone domain. The top cuts were established on the basis of statistical analysis and were applied to the assays before calculation of composite grades. A GMV cut‐off of US$75/tonne is derived from the value of Sn, Zn and In for each block and the GMV cut‐off is based on the assumption that the deposit is of a potential size and nature to allow for possible bulk mining methods.

A copy of the full mineral resource estimate will be available in a NI‐43‐101‐compliant report on the SEDAR website within 45 days of this press release. That report will be prepared by Michael Kociumbas,  B.Sc.,  P.Geo.  and  Vice‐President   of  Watts,  Griffis  and  McOuat  Limited,  Steve McCutcheon,  Ph.D.,  P.Geo.,  of  McCutcheon  Geo‐Consulting,  John  Reddick,  M.Sc.,  P.Geo.,  of Reddick Consulting Inc., and Mohan Srivastava, M.Sc., P.Geo., of FSS Canada Consultants Inc. The mineral resource estimates, which are effective today, were completed by John Reddick, M.Sc., P.Geo., of Reddick Consulting Inc. and Mohan Srivastava, M.Sc., P.Geo., of FSS Canada Consultants  Inc.,  and  are  based  on  geological  interpretations  and  data  supplied  by  the Company.  Michael Kociumbas, John Reddick and Mohan Srivastava are ‘independent qualified persons’  for  the  purposes  of  NI  43‐101  Standards  of  Disclosure  for  Mineral  Projects  of  the Canadian Securities Administrators and have verified the mineral resource data disclosed in this release. Steve McCutcheon, Ph.D., P.Geo., of McCutcheon Geo‐Consulting and an ‘independent qualified person’ for the purposes of NI 43‐101 Standards of Disclosure for Mineral Projects of the Canadian Securities Administrators, has verified the sampling procedures and QA/QC data delivered to WGM and is of the opinion that the data are of good quality and suitable for use in the mineral resource estimates.

McCutcheon,  Srivastava  and  Reddick  approved  the  disclosure  of  the  technical  information contained in this press release. This release has also been reviewed by Adex’s Chief Operating Officer Patrick Merrin, P. Eng.

ABOUT ADEX 

Adex Mining Inc. is a Canadian junior mining company with an experienced management team. The Company is focused on developing its flagship Mount Pleasant Mine property, a multi‐metal project  that  is  host  to  promising  tungsten‐molybdenum  and  tin‐indium‐zinc  mineralization. Located  in  Charlotte  County,  New  Brunswick,  the  property  is  situated  approximately  80  km south  of  Fredericton,  the  provincial  capital,  and  65  km  from  the  United  States  border.  The common shares of Adex trade on the TSX Venture Exchange under the stock symbol “ADE.”

No securities commission or regulatory authority has approved or disapproved the contents of  this press release.  

The TSX Venture Exchange does not accept responsibility for the adequacy or accuracy of this  press release. 

CONTACT INFORMATION 

Adex Mining Inc.

Linda Lam Kwan Interim President, Chief Executive Officer and Director 1‐866‐508‐2339 (ADEX)

Email: [email protected] Website: www.adexmining.com

FORWARD‐LOOKING STATEMENTS 

Certain  statements  in  this  press  release  may  constitute  "forward‐looking"  statements  which involve  known  and  unknown  risks,  uncertainties  and  other  factors  which  may  cause  actual results,  performance  or  achievements  of  Adex,  its  subsidiary  or  the  industry  in  which  they operate  to  be  materially  different  from  any  future  results,  performance  or  achievements expressed or implied by such forward‐looking statements. When used in this press release, the words "estimate", "believe", "anticipate", "intend", "expect", "plan", "may", "should", "will", the negative thereof or other variations thereon or comparable terminology are intended to identify forward‐looking  statements.  Such  statements  reflect  the  current  expectations  of  the management of Adex with respect to future events based on currently available information and are  subject  to  risks  and  uncertainties  that  could  cause  actual  results,  performance  or achievements  to  differ  materially  from  those  expressed  or  implied  by  those  forward‐looking statements.  These  risks  and  uncertainties  are  detailed  from  time  to  time,  including,  without limitation, under the heading "Risk Factors", in reports filed by Adex with the Alberta, British Columbia  and  Ontario  Securities  Commissions  which  are  available  at  www.sedar.com  and  to which readers of this press release are referred for additional information concerning Adex, its prospects and the risks and uncertainties relating to Adex and its prospects. New risk factors may arise from time to time and it is not possible for management to predict all of those risk factors or the extent to which any factor or combination of factors may cause actual results, performance  and  achievements  of  Adex  to  be  materially  different  from  those  contained  in forward‐looking statements. Although the forward‐looking statements contained in this press release are based upon what management believes to be reasonable assumptions, Adex cannot assure investors that actual results will be consistent with these forward‐looking statements. Given  these  risks  and  uncertainties,  investors  should  not  place  undue  reliance  on  forward‐ looking statements as a prediction of actual results.

The forward‐looking information contained in this press release is current only as of the date of the press release.  Adex does not undertake or assume any obligation to release publicly any revisions to these forward‐looking statements to reflect events or circumstances after the date hereof or to reflect the occurrence of unanticipated events, except as required by law.