Asanko Gold Mine Approved for Construction

Financings Mine Development & Operations

Highlights:  

  • Board  approval  to  proceed  with  construction  of  fully  permitted  Phase  1  Asanko  Gold  Mine.
  • Capital   Control   Budget   Estimate   (“CBE”)   of   US$295   million,   in-­‐line   with   Definitive   Feasibility   Study1 (“DFS”),  and  fully  financed  with  US$231million2  cash  and  US$150  million3  project  debt  facility.
  • Preliminary  mine  planning,  based  on  the  updated  Mineral  Resource  Estimate  (“MRE”),  confirms  mine plan  in-­‐line  with  DFS,  producing  2.25  million  ounces  of  gold  over  11.5  year  life  of  mine  (“LoM”).
  • Definitive  Project  Plan  with  updated  MRE  to  be  published  as  an  NI  43-­‐101  compliant  technical  report by  Q4  2014.

Ground  breaking  planned  in  Q3  2014  with  first  gold  pour  expected  in  Q1  2016.

•

Vancouver,  British  Columbia,  July  17  2014  –  Asanko  Gold  Inc.  (“Asanko”  or  the  “Company”)  (TSX,  NYSE   MKT:  AKG)  is  pleased  to  announce  that  the  Board  of  Directors  have  made  a  positive  financial  investment decision  to  proceed  with  the  construction  of  Phase  1  of  the  Asanko  Gold  Mine  (“AGM”  or  the  “Project”)  in Ghana.

Phase  1  is  based  on  the  construction  of  the  Obotan  Gold  Project  which  was  acquired  during  the  takeover  of PMI   Gold   Corporation   (“PMI   Gold”)   in   February   2014.   Phase   2   anticipates   the   inclusion   of   the   adjacent Esaase  deposit.    Early  works  at  the  project  site  has  been  underway  since  April  in  preparation  for  a  positive investment  decision  with  progress  on  schedule.    Project  construction  will  commence  shortly,  with  ground breaking  expected  within  the  next  month.  First  gold  is  targeted  in  Q1  2016,  with  steady  stage  production anticipated  in  Q2  2016.

Asanko’s  President  and  CEO,  Peter  Breese,  said:  “The  Board’s  approval  of  Phase  1  of  the  Asanko  Gold  Mine   is  the  first  step  towards  achieving  our  vision  of  becoming  a  mid-­‐tier  gold  producer.    Our  detailed  engineering   work  to-­‐date  has  confirmed  the  robustness  of  the  Project,  with  the  CBE  in-­‐line  with  PMI  Gold’s  2012  DFS.   Now  that  we  have  approved  the  Project,  we  are  targeting  steady  state  production  of  approximately  200,000   ounces  per  year  in  Q2  2016.      

With  the  Project  fully  permitted,  financed  and  a  team  of  experienced  mine  builders  and  operators  in  place,   we  will,  in  parallel  with  construction,  continue  with  our  growth  strategy.    In  particular  we  have  begun  to   evaluate   the   optimal   way   to   implement   Phase   2   in   order   to   bring   to   account   the   additional   2.2   million   ounces  of  Mineral  Reserves4  at  Esaase,  while  capturing  the  synergies  we  forecast  when  we  acquired  PMI   Gold  and  created  the  Asanko  Gold  Mine.”  

Asanko  Gold  Mine  -­‐  Phase  1  

Phase  1  is  based  on  PMI  Gold’s  DFS  for  the  Obotan  Project,  published  in  September  2012.    The  DFS  targeted approximately  2.25  million  ounces  of  gold  production  over  an  11.5  year  LoM  via  an  open  pit  contractor mining   operation   and   a   3Mtpa   carbon-­‐in-­‐leach   (“CIL”)   processing   plant.     The   primary   source   of   feed material  for  the  CIL  plant  was  the  Nkran  pit  with  satellite  pits  at  Adubiaso,  Abore  and  Asuadai  being  mined later   in   the   mine   life.     The   DFS   estimated   capital   costs   of   US$296.6   million,   cash   operating   costs   of US$626/oz   (US$722/oz   including   royalty   and   refining   costs)   and   projected   robust   economic   returns   at US$1,300/oz  gold.

Since  acquiring  PMI  Gold  earlier  this  year,  the  Company  has  updated  the  capital  cost  estimate  to  a  higher level  of  accuracy  suitable  for  use  as  a  project  CBE.    The  recently  completed  CBE  estimates  a  capital  cost  of US$295  million  including  contingency  for  estimating  inaccuracy  and  owner’s  contingency  (see  table  below). The  capital  estimate  is  generally  considered  accurate  to  +/-­‐  5%.

The  CBE  was  designed  on  a  modular  basis  to  cater  for  the  possible  inclusion  of  Phase  2  of  the  AGM  on  the same   site.     Phase   1   has   incorporated   sufficient   plant   terracing   and   designed   the   plant   layout   and infrastructure  to  cater  for  the  potential  of  Phase  2.

Asanko Gold Mine – Phase 1Capital Estimate (US$ million)
Process plant85.48
Mining (pre-­‐production costs)70.59
Power infrastructure18.18
Buildings, offices and accommodation12.31
TSF, WRD, ROM, water supply, civil works23.08
CSR, owners team, G&A47.37
EPCM15.51
Sub total272.52
Contingency & estimating inaccuracies22.75
Total295.27

Asanko  is  currently  finalizing  the  updated  MRE  for  the  Nkran,  Adubiaso,  Abore  and  Asuadai  deposits  and does   not   anticipate   that   the   MRE   will   be   materially   different   to   the   current   disclosure.     Based   on   the revised  MRE,  a  preliminary  mine  plan  has  been  prepared.    The  Definitive  Project  Plan  is  not  expected  to  be materially  different  to  the  DFS  mining  plan  of  2.25  million  ounces  of  gold  produced  over  an  11.5  year  LoM.

The  Company  is  continuing  to  work  on  detailed  mine  planning  and  pit  sequencing  optimizations,  including  a mine  plan  for  the  recently  discovered  near-­‐mine  deposit  Dynamite  Hill.    This  detailed  mine  plan  will  be included   in   the   Definitive   Project   Plan,   along   with   updated   operating   costs   and   economic   return calculations.    The  results  of  the  Definitive  Project  Plan  are  expected  to  be  published  by  Q4  2014  in  a  revised NI  43-­‐101  report  for  the  Project.

Phase  1  Project  Schedule  and  Key  Milestones  

The  Company’s  key  Project  timelines  remain  on  schedule:

Original  Guidance   Current  Status   Commence  early  works     Q2  2014     Nearing  Completion Near  mine  resource  definition  drilling  at  Dynamite  Hill   Q2  2014   Complete Finalize  revisions  to  the  Red  Kite  financing  arrangements   Q2  2014   Complete Investment  Decision  for  Phase  1   Q3  2014   Complete Definitive  Project  Plan  including  updated  MRE   Q4  2014   Ongoing Commence  Project  Construction   Q3  2014   Start  -­‐  August Evaluate  trade  off  studies  for  Phase  2   Q4  2014   Underway Commissioning  and  Ramp-­‐up   Q1  2016     Q1  2016 Steady  State  Production  of  >200,000  oz/year   Q2  2016   Q2  2016

Enquiries:  

For  further  information  please  visit  www.asanko.com  or  contact:

Alex  Buck,  Manager  –  Investor  Relations   Greg  McCunn,  Chief  Financial  Officer Telephone:  +44-­‐7932-­‐740-­‐452   Telephone:  +1-­‐778-­‐729-­‐0604 Email:  [email protected]   Email:  [email protected]

General  [email protected]

Notes:  

1. PMI  Gold  Corporation’s  Definitive  Feasibility  Study  (“DFS”)  on  the  Obotan  Project,  published  in September  2012.    See  filing  on  www.sedar.com.

2. Estimated  cash  balance  as  at  June  30,  2014.

3. Project  debt  facility  arranged  with  Red  Kite  Mine  Finance.    See  news  release  dated  July  14,  2014.

4. Mineral  Reserve  for  Esaase  contains  22.9Mt  grading  1.43g/t  Au  for  1.05  million  ounces  of  Proven  and 22.5Mt  grading  1.40g/t  Au  containing  1.32  million  ounces  of  Probable  as  reported  in  the  NI43-­‐101 Technical  Report  filed  on  SEDAR  on  June  27,  2013.

About  Asanko  Gold  Inc.  

Asanko’s  vision  is  to  become  a  mid-­‐tier  gold  mining  company  that  maximizes  value  for  all  its  stakeholders. Asanko’s  flagship  project  is  the  fully  financed  and  permitted,  multi-­‐million  ounce  Asanko  Gold  Mine  Project located  in  Ghana,  West  Africa.  The  mine  will  be  developed  in  phases.    Phase  1  has  been  approved  and construction  will  commence  in  Q3  2014,  with  first  gold  is  targeted  in  Q1  2016.

Asanko  is  managed  by  highly  skilled  and  successful  technical,  operational  and  financial  professionals.  The Company   is   strongly   committed   to   the   highest   standards   for   environmental   management,   social responsibility,  and  health  and  safety  for  its  employees  and  neighbouring  communities.

Forward-­‐Looking  and  other  Cautionary  Information

This   release   includes   certain   statements   that   may   be   deemed   "forward-­‐looking   statements".   All   statements   in   this   release,  other  than  statements  of  historical  facts,  that  address  estimated  resource  quantities,  grades  and  contained   metals,  possible  future  mining,  exploration  and  development  activities,  are  forward-­‐looking  statements.  Although  the   Company  believes  the  forward-­‐looking  statements  are  based  on  reasonable  assumptions,  such  statements  should  not   be  in  any  way  construed  as  guarantees  of  future  performance  and  actual  results  or  developments  may  differ  materially   from  those  in  the  forward-­‐looking  statements.  Factors  that  could  cause  actual  results  to  differ  materially  from  those  in   forward-­‐looking   statements   include   market   prices   for   metals,   the   conclusions   of   detailed   feasibility   and   technical   analyses,  lower  than  expected  grades  and  quantities  of  resources,  mining  rates  and  recovery  rates  and  the  lack  of   availability  of  necessary  capital,  which  may  not  be  available  to  the  Company  on  terms  acceptable  to  it  or  at  all.  The   Company   is   subject   to   the   specific   risks   inherent   in   the   mining   business   as   well   as   general   economic   and   business   conditions.  For  more  information  on  the  Company,  Investors  should  review  the  Company's  annual  Form  20-­‐F  filing  with   the  United  States  Securities  Commission  and  its  home  jurisdiction  filings  that  are  available  at  www.sedar.com.  

Neither  Toronto  Stock  Exchange  nor  the  Investment  Industry  Regulatory  Organization  of  Canada  accepts  responsibility   for  the  adequacy  or  accuracy  of  this  release.  

Cautionary  Note  to  US  Investors  Regarding  Mineral  Reporting  Standards:  

Asanko  has  prepared  its  disclosure  in  accordance  with  the  requirements  of  securities  laws  in  effect  in  Canada,  which   differ  from  the  requirements  of  US  securities  laws.  Terms  relating  to  mineral  resources  in  this  press  release  are  defined   in  accordance  with  National  Instrument  43-­‐101  -­‐  Standards  of  Disclosure  for  Mineral  Projects  under  the  guidelines  set   out   in   the   Canadian   Institute   of   Mining,   Metallurgy,   and   Petroleum   Standards   on   Mineral   Resources   and   Mineral   Reserves.    The  Securities  and  Exchange  Commission  (the  “SEC”)  permits  mining  companies,  in  their  filings  with  the  SEC,   to  disclose  only  those  mineral  deposits  that  a  company  can  economically  and  legally  extract  or  produce.    Asanko  uses   certain  terms,  such  as,  “measured  mineral  resources”,  “indicated  mineral  resources”,  “inferred  mineral  resources”  and   “probable  mineral  reserves”,  that  the  SEC  does  not  recognize  (these  terms  may  be  used  in  this  press  release  and  are   included   in   the   public   filings   of   Asanko   which   have   been   filed   with   securities   commissions   or   similar   authorities   in   Canada).  

Qualified  Persons  Statement  

Qualified Persons in Respect of Technical Disclosure

The information in this release that relates to Esaase Mineral Reserves is based on information compiled by Mr. Thomas Obiri-Yeboah. Mr. Thomas Obiri-Yeboah is the Senior Mining Engineer of DRA Mineral Projects Mining Division. Mr. Thomas Obiri-Yeboah is a Member of the South African Institute of Mining and Metallurgy and has sufficient experience which is relevant to the style of mineralization and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code) and is a "Qualified Person" under National Instrument 43-101 - 'Standards of Disclosure for Mineral Projects'. He has verified the Esaase reserve data disclosed in this news release.

The information in this release that relates to Esaase in-situ Mineral Resources is based on information compiled by Mr Charles Muller of Minxcon. He is a Member of the Australasian Institute of Mining and Metallurgy and has sufficient experience, which is relevant to the style of mineralisation and type of deposit under consideration, and to the activity he is undertaking, to qualify as a Competent Person as defined in the 2004 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (The JORC Code) and is a "Qualified Person" under National Instrument 43-101 - 'Standards of Disclosure for Mineral Projects'. He has verified the data disclosed in this release in connection with Esaase including sampling, analytical and test data underlying the information contained in this release. Mr Muller consents to the inclusion of such information in this release in the form and context in which it appears.

Information that relates to Mineral Resources at the Obotan Gold Project is based on a resource estimate that has been carried out by Mr Peter Gleeson, a full time employee of SRK Consulting. Mr Gleeson is a Member of the Australian Institute of Geoscientists (MAIG). Information that relates to Mineral Reserves at the Obotan Gold Project is based on a reserve estimate that has been carried out by Mr Ross Cheyne, a full time employee of Orelogy Mining Consultants. Mr Cheyne is a Fellow of the Australasian Institute of Mining and Metallurgy (FAusIMM). Both have sufficient experience which is relevant to the style of mineralization and type of deposit under consideration and to the activity undertaken to qualify as a Competent Person as defined in the 2004 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (JORC), and as a Qualified Person (by ROPO) as defined in terms of NI43-101 standards for resource estimate of gold. Mr Gleeson and Mr Cheyne have more than 5 years' experience in the field of exploration results and of resource/reserve estimation and consent to and approve the inclusion of matters based on information in the form and context in which it appears.

The Mineral Resource and Mineral Reserve estimates have been prepared in accordance with the 2010 Canadian Institute of Mining, Metallurgy and Petroleum (CIM) Definition Standards for Mineral Resources and Mineral Reserve as incorporated by reference in National Instrument 43-101 of the Canadian Securities Administrators, and is consistent with the Australasian Guidelines and Code for the Reporting of Exploration Results, Mineral Resources and Ore Reserves (Revised December 2007) as prepared by the Joint Ore Reserves Committee of the AusIMM, AIG and MCA (JORC).